TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/MH/Others/35246/2018              (ii). Name of Project for which Forest Land is required : Gas Distribution network in Talasari Taluka of Palghar District - Angam Spurline & Angam CNG Connectivity              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of 0.1320 Hect of Protected/Private (35 Section) Forest land for laying natural gas pipeline from Sanjan to Angam – Pipeline laying through Protected/Private (35 Section) Forest Lands in village Amgaon & Uplat, Taluka Talasari, District Palghar of Maharashtra State.              (iv). File no. : FLD-2021/CR-132/F-10              (v). State : Maharashtra              (vi). Category of the Project : Others              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.132
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/MH/Others/35246/201810/08/201813/08/2018   10/09/2018   11/09/2018   22/09/2018 Dahanu :27/09/2018Thane:
  05/10/2019 (Dahanu)

Maharashtra:
21/09/2020
Maharashtra:
21/01/2021
23/07/2021
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Circle (Thane) on:06/11/2019  
Replied by DFO (Dahanu) on:17/09/2020  
Query raised by DFO (Dahanu) on:24/05/2019  
Replied by UA on :25/05/2019  
Query raised by DFO (Dahanu) on:19/07/2019  
Replied by UA on :09/08/2019  
D. Essential Details Sought History (Stage-II)
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
   Query raised by State Government (Maharashtra) on:25/06/2024  
Query raised by Nodal Officer on:22/07/2024  
Replied by UA on :24/02/2025  
Query raised by Nodal Officer on:27/02/2025  
Replied by UA on :  
NOTE:- Proposal is pending at User Agency due to EDS raised by State Government for verifying Compliance of Conditions .