Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Pune)
|
EDS
|
User Agency (sde_bsnlpune@enviroconcern.in)
|
20/11/2021
|
Letter No 238 Dt 18.11.2021
|
|
2
|
User Agency (sde_bsnlpune@enviroconcern.in)
|
REPLY
|
DFO (Pune)
|
27/05/2022
|
The correction have been made as per the instruction received
|
|
3
|
Nodal Officer
|
EDS
|
CF (Pune)
|
09/06/2022
|
Query raised by this office letter dt 09-06-22
|
|
4
|
CF (Pune)
|
EDS
|
DFO (Pune)
|
15/06/2022
|
for compliance
|
|
5
|
DFO (Pune)
|
EDS
|
User Agency (sde_bsnlpune@enviroconcern.in)
|
15/07/2022
|
Query
|
|
6
|
User Agency (sde_bsnlpune@enviroconcern.in)
|
REPLY
|
DFO (Pune)
|
17/08/2022
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Pune)
|
EDS
|
User Agency (sde_bsnlpune@enviroconcern.in)
|
19/08/2022
|
Query by this office letter No 145 dt 05.08.2022
|
|
8
|
User Agency (sde_bsnlpune@enviroconcern.in)
|
REPLY
|
DFO (Pune)
|
22/08/2022
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Pune)
|
EDS
|
User Agency (sde_bsnlpune@enviroconcern.in)
|
29/08/2022
|
area query
|
|
10
|
User Agency (sde_bsnlpune@enviroconcern.in)
|
REPLY
|
DFO (Pune)
|
02/09/2022
|
The correction have been made as per the instruction received
|
|
11
|
DFO (Pune)
|
EDS
|
User Agency (sde_bsnlpune@enviroconcern.in)
|
07/12/2022
|
query
|
|
12
|
User Agency (sde_bsnlpune@enviroconcern.in)
|
REPLY
|
DFO (Pune)
|
21/05/2023
|
The correction have been made as per the instruction received
|
|
13
|
DFO (Pune)
|
EDS
|
User Agency (sde_bsnlpune@enviroconcern.in)
|
20/06/2023
|
query compliace as per apccf & nodal officer letter no.840 dt.19/06/2023
|
|
14
|
User Agency (sde_bsnlpune@enviroconcern.in)
|
REPLY
|
DFO (Pune)
|
23/11/2023
|
The correction have been made as per the instruction received
|
|
15
|
DFO (Pune)
|
REPLY
|
CF (Pune)
|
05/12/2023
|
query compliance
|
|
16
|
CF (Pune)
|
REPLY
|
Nodal Officer
|
09/01/2024
|
query compliance
|
|
17
|
Regional Office
|
EDS
|
State secretary
|
29/01/2024
|
The instant proposal herewith returned to the State Government with a request to take action under 3A/3B and submit the proposal directly to the MoEF&CC, New Delhi.
|
|
18
|
State secretary
|
EDS
|
Nodal Officer
|
29/01/2024
|
for necessary action
|
|
19
|
Nodal Officer
|
REPLY
|
State secretary
|
29/01/2024
|
Query Compliance
|
|
20
|
State secretary
|
EDS
|
Nodal Officer
|
21/02/2024
|
The instant proposal involves work in violation of Adhiniyam. Hence as per the provisions of Van Sanrakshan Evam Samvardhan Rules 2023 competency to deal with such violation cases is MoEF&CC, New Delhi. Therefore, change the Scenario for submit proposal to MoEF&CC, New Delhi.
|
|
21
|
Nodal Officer
|
EDS
|
CF (Pune)
|
23/02/2024
|
Query raised by this office letter Dated 23/02/2024
|
|
22
|
CF (Pune)
|
REPLY
|
Nodal Officer
|
14/03/2024
|
Query compliance
|
|
23
|
Nodal Officer
|
EDS
|
CF (Pune)
|
03/04/2024
|
For Physical copy submission.
|
|
24
|
CF (Pune)
|
REPLY
|
Nodal Officer
|
03/05/2024
|
query compliance
|
|
25
|
Nodal Officer
|
REPLY
|
State secretary
|
15/05/2024
|
Violation report
|
|
26
|
State secretary
|
REPLY
|
Regional Office
|
22/05/2024
|
for necessary action
|
|
27
|
Regional Office
|
EDS
|
State secretary
|
27/05/2024
|
As the proposal involves work in violation of Adhiniyam 1980 and the proposal is dealing by the Ministry, the proposal may be forwarded to the Ministry in consultation with the NIC new delhi
|
|
28
|
State secretary
|
EDS
|
Nodal Officer
|
20/07/2024
|
For necesary action
|
|
29
|
Nodal Officer
|
EDS
|
CF (Pune)
|
22/07/2024
|
Query raised by this office letter Dated -7/06/2024
|
|
30
|
CF (Pune)
|
EDS
|
DFO (Pune)
|
22/07/2024
|
Query raised by this office letter dated B 839 Dt. 29/06/2024
|
|
31
|
DFO (Pune)
|
EDS
|
User Agency (sde_bsnlpune@enviroconcern.in)
|
22/07/2024
|
State Government has uploaded) Shape file/ KML file over an area of 0.764 ha of forest land instead of 0.28 ha. Therefore, the State Govt. is requested to upload the correct KML file of 0.28 ha proposed forest land.
|
|
32
|
User Agency (sde_bsnlpune@enviroconcern.in)
|
REPLY
|
DFO (Pune)
|
22/07/2024
|
The correction have been made as per the instruction received
|
|
33
|
DFO (Pune)
|
EDS
|
User Agency (sde_bsnlpune@enviroconcern.in)
|
22/07/2024
|
Please submit corrected map
|
|
34
|
User Agency (sde_bsnlpune@enviroconcern.in)
|
REPLY
|
DFO (Pune)
|
22/07/2024
|
The correction have been made as per the instruction received
|
|
35
|
DFO (Pune)
|
REPLY
|
CF (Pune)
|
22/07/2024
|
Query compliance this office letter no. 538 Date - 19.07.2024
|
|
36
|
CF (Pune)
|
REPLY
|
Nodal Officer
|
22/07/2024
|
Query compliance is done
|
|
37
|
Nodal Officer
|
REPLY
|
State secretary
|
22/07/2024
|
Query Compliance
|
|
38
|
State secretary
|
EDS
|
Nodal Officer
|
08/08/2024
|
for necessary action
|
|
39
|
Nodal Officer
|
REPLY
|
State secretary
|
09/08/2024
|
Information submitted by E mail dt 08-09-2024
|
|
40
|
State secretary
|
REPLY
|
Regional Office
|
18/09/2024
|
for necessary action
|
|