TimeLine Details
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
Proposal received date at each stage of flow.
A.
General Details
(i). Proposal No. :
FP/MH/MIN/6398/2014
(ii). Name of Project for which Forest Land is required :
HLOC Mine
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
HLOC Expansion Project
(iv). File no. :
8-115/1995-FC Vol.
(v). State :
Maharashtra
(vi). Category of the Project :
Mining
(vii). Shape of forest land proposed to be diverted :
Non Linear
(viii). Area of forest land proposed for diversion(in ha.):
36.98
B.
Time Line
Proposal No.
Submitted by User Agency
Query for Shortcoming(if any) by Nodal Officer
Resubmission of Proposal by User Agency
Query by Nodal Officer for submitting Hard Copies
Uploading(by U.A.) of copies of receipt received from DFO & DC
Division
Circle
Nodal Office
State Government
MoEFCC,New Delhi
Stage-I Approval on
Compliance Report Submitted by State on
Stage-II Approval on
FP/MH/MIN/6398/2014
08/08/2014
04/12/2014
31/10/2014
07/10/2014
08/09/2014
08/12/2014
18/11/2014
20/10/2014
29/09/2014
08/12/2014
11/03/2015
Chandrapur
:
12/03/2015
Chandrapur
:
03/08/2015 (
Chandrapur
)
Maharashtra
:
12/08/2015
Maharashtra
:
10/09/2015
06/06/2017
16/04/2018
By :Head Office
Maharashtra
03/12/2019
28/09/2020
By :Head Office
C. Essential Details Sought History
 
Communication between MoEFCC,New Delhi & State Government
Communication between State Government & Nodal Officer
Communication between Nodal Officer & Circle
Communication between Circle & Division
Communication between Division & User Agency
Query raised by MoEFCC,New Delhi on
13/09/2017
Replied by State Government (Maharashtra) on:
05/01/2018
NOTE:-
Stage-II Approval accorded by :
Head Office
.
Close(X)
Close(X)
Please wait ...
EDS History
×
EDS History
×
Proposal No.-
Sno.
From
Status
To
EDS Date
EDS sought/Replied
EDS Letter
1
Head Office
EDS
State secretary
13/09/2017
EDS
2
State secretary
REPLY
Head Office
05/01/2018
Nodal Office Reply on dt. 30/11/2017 submitted herewith.
EDS History(Stage-II)
×