TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/MH/IRRIG/15702/2015              (ii). Name of Project for which Forest Land is required : Surewada Lift Irrigation Scheme              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Construction of Surewada LIS include Pump House, Rising Main, Delevary chamber, Main Canal and its Distributory System              (iv). File no. : FC-II/MH-41/2016-NGP              (v). State : Maharashtra              (vi). Category of the Project : Irrigation              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 37.512
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/MH/IRRIG/15702/201505/10/201516/10/2015   06/11/2015   06/11/2015   10/11/2015 Bhandara:  10/11/2015
Gondia WL:  10/11/2015
Gondia(Nagpur):  10/11/2015
Nagpur:
  04/10/2016 (Gondia(Nagpur))

Nagpur:
  04/10/2016 (Bhandara)

Wildlife Nagpur:
  05/10/2016 (Gondia WL)

Maharashtra:
05/10/2016
Maharashtra:
05/10/2016
Nagpur:
05/10/2016
12/06/2017
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Nagpur) on:27/10/2016  
Replied by State Government(Maharashtra) on:31/01/2018  
Query raised by DFO (Gondia(Nagpur)) on:29/12/2015  
Replied by UA on :30/12/2015  
NOTE:- Stage-I Approval accorded by : Regional Office .