| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
DFO (Sawantwadi)
|
EDS
|
User Agency (nirukheee@gmail.com)
|
21/10/2021
|
Inspection of diverted land site
|
|
|
2
|
User Agency (nirukheee@gmail.com)
|
REPLY
|
DFO (Sawantwadi)
|
20/12/2021
|
The correction have been made as per the instruction received
|
|
|
3
|
DFO (Sawantwadi)
|
EDS
|
User Agency (nirukheee@gmail.com)
|
14/04/2022
|
Update CA land details
|
|
|
4
|
User Agency (nirukheee@gmail.com)
|
REPLY
|
DFO (Sawantwadi)
|
16/04/2022
|
The correction have been made as per the instruction received
|
|
|
5
|
CF (Kolhapur)
|
EDS
|
DFO (Sawantwadi)
|
10/05/2022
|
Pls Update Part - I & II
|
|
|
6
|
DFO (Sawantwadi)
|
EDS
|
User Agency (nirukheee@gmail.com)
|
10/05/2022
|
Pls Update Part - I & II
|
|
|
7
|
User Agency (nirukheee@gmail.com)
|
REPLY
|
DFO (Sawantwadi)
|
20/05/2022
|
The correction have been made as per the instruction received
|
|
|
8
|
DFO (Sawantwadi)
|
EDS
|
User Agency (nirukheee@gmail.com)
|
31/05/2022
|
Add FRA
|
|
|
9
|
User Agency (nirukheee@gmail.com)
|
REPLY
|
DFO (Sawantwadi)
|
31/05/2022
|
The correction have been made as per the instruction received
|
|
|
10
|
DFO (Sawantwadi)
|
REPLY
|
CF (Kolhapur)
|
31/05/2022
|
Part -1 and II uploaded
|
|
|
11
|
CF (Kolhapur)
|
EDS
|
DFO (Sawantwadi)
|
31/05/2022
|
Pl Upload FRA In Part I
|
|
|
12
|
DFO (Sawantwadi)
|
REPLY
|
CF (Kolhapur)
|
31/05/2022
|
Respected Sir,
FRA and Part I uploaded
|
|
|
13
|
Nodal Officer
|
EDS
|
CF (Kolhapur)
|
13/07/2022
|
Query raised by this office letter dt 13-07-22
|
|
|
14
|
CF (Kolhapur)
|
EDS
|
DFO (Sawantwadi)
|
18/07/2022
|
Pl comply query raised by Nodal office letter dt 13-07-22
|
|
|
15
|
DFO (Sawantwadi)
|
EDS
|
User Agency (nirukheee@gmail.com)
|
08/08/2022
|
Certificate number 9 update
|
|
|
16
|
User Agency (nirukheee@gmail.com)
|
REPLY
|
DFO (Sawantwadi)
|
30/08/2022
|
The correction have been made as per the instruction received
|
|
|
17
|
DFO (Sawantwadi)
|
REPLY
|
CF (Kolhapur)
|
30/08/2022
|
Respected Sir,
The correction has been done as per instruction
|
|
|
18
|
CF (Kolhapur)
|
REPLY
|
Nodal Officer
|
19/09/2022
|
Compliance report submitted
|
|
|
19
|
State secretary
|
EDS
|
Nodal Officer
|
17/11/2022
|
for further necessary action
|
|
|
20
|
Nodal Officer
|
EDS
|
CF (Kolhapur)
|
22/11/2022
|
For query compliance
|
|
|
21
|
CF (Kolhapur)
|
EDS
|
DFO (Sawantwadi)
|
22/11/2022
|
For query compliance
|
|
|
22
|
DFO (Sawantwadi)
|
EDS
|
User Agency (nirukheee@gmail.com)
|
30/11/2022
|
Complete compliance letter awaited from UA
|
|
|
23
|
User Agency (nirukheee@gmail.com)
|
REPLY
|
DFO (Sawantwadi)
|
15/12/2022
|
The correction have been made as per the instruction received
|
|
|
24
|
DFO (Sawantwadi)
|
REPLY
|
CF (Kolhapur)
|
15/12/2022
|
Respected sir
The compliance has been done
|
|
|
25
|
CF (Kolhapur)
|
REPLY
|
Nodal Officer
|
04/01/2023
|
Compliance report submitted
|
|
|
26
|
Nodal Officer
|
REPLY
|
State secretary
|
09/01/2023
|
Query compliance
|
|
|
27
|
Regional Office
|
EDS
|
State secretary
|
17/04/2023
|
Addl Info sought
|
|
|
28
|
State secretary
|
EDS
|
Nodal Officer
|
18/04/2023
|
Addl Info sought
|
|
|
29
|
Nodal Officer
|
EDS
|
CF (Kolhapur)
|
19/04/2023
|
For query compliance
|
|
|
30
|
CF (Kolhapur)
|
EDS
|
DFO (Sawantwadi)
|
21/04/2023
|
For query compliance
|
|
|
31
|
DFO (Sawantwadi)
|
EDS
|
User Agency (nirukheee@gmail.com)
|
05/06/2023
|
Complete compliance letter awaited from UA
|
|
|
32
|
User Agency (nirukheee@gmail.com)
|
REPLY
|
DFO (Sawantwadi)
|
21/06/2023
|
The correction have been made as per the instruction received
|
|
|
33
|
DFO (Sawantwadi)
|
EDS
|
User Agency (nirukheee@gmail.com)
|
28/07/2023
|
For query compliance
|
|
|
34
|
User Agency (nirukheee@gmail.com)
|
REPLY
|
DFO (Sawantwadi)
|
24/08/2023
|
The correction have been made as per the instruction received
|
|
|
35
|
DFO (Sawantwadi)
|
REPLY
|
CF (Kolhapur)
|
24/08/2023
|
Correction has been done
Kindly please check
|
|
|
36
|
CF (Kolhapur)
|
REPLY
|
Nodal Officer
|
25/08/2023
|
Compliance report submitted
|
|
|
37
|
Nodal Officer
|
REPLY
|
State secretary
|
25/08/2023
|
Query Compliance
|
|
|
38
|
State secretary
|
REPLY
|
Regional Office
|
29/08/2023
|
for further necessary action
|
|
|
39
|
Regional Office
|
EDS
|
State secretary
|
27/10/2023
|
Not received
|
|
|
40
|
State secretary
|
REPLY
|
Regional Office
|
22/11/2023
|
Regional Office, MoEF&CC, GoI, Nagpur has received hard copy of the Compliance Report with annexures, on 02.11.2023.
|
|