TimeLine Details
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
Proposal received date at each stage of flow.
A.
General Details
(i). Proposal No. :
FP/KL/WATER/126847/2021
(ii). Name of Project for which Forest Land is required :
Sabarimala Master Plan - CWSS to Pampa & Sabarimala - Construction of 10LL OHSR at Pampa
(iii). Short narrative of the proposal and Project/scheme for which the forest land is required :
Construction of 10LL storage capacity Overhead Service Reservoir having total 21Mtrs height at Pampa for improving water scarcity of pilgrims enroute Sabarimala.
(iv). File no. :
C3/249/2021/F&WLD
(v). State :
Kerala
(vi). Category of the Project :
Drinking Water
(vii). Shape of forest land proposed to be diverted :
Non Linear
(viii). Area of forest land proposed for diversion(in ha.):
0.07
B.
Time Line
Proposal No.
Submitted by User Agency
Query for Shortcoming(if any) by Nodal Officer
Resubmission of Proposal by User Agency
Query by Nodal Officer for submitting Hard Copies
Uploading(by U.A.) of copies of receipt received from DFO & DC
Division
Circle
Nodal Office
State Government
Stage-I Approval on
Stage-II Approval on
FP/KL/WATER/126847/2021
03/04/2021
06/05/2021
26/05/2021
24/06/2021
29/06/2021
Ranni
:
12/07/2021
Southern Circle, Kollam
:
16/07/2021 (
Ranni
)
Kerala
:
10/09/2021
Kerala
:
28/01/2022
01/02/2022
By :State Government
C. Essential Details Sought History
 
Communication between Regional Office & State Government
Communication between State Government & Nodal Officer
Communication between Nodal Officer & Circle
Communication between Circle & Division
Communication between Division & User Agency
NOTE:-
Stage-I Approval accorded by :
State Government
.
Close(X)
Close(X)
Please wait ...
EDS History
×
EDS History
×
Proposal No.-
Sno.
From
Status
To
EDS Date
EDS sought/Replied
EDS Letter
No Record Available
EDS History(Stage-II)
×