TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/KL/VELEC/51441/2020              (ii). Name of Project for which Forest Land is required : CONSTRUCTING 560M OVERHEAD ELECTRIC LINE FOR PROVIDING SERVICE CONNECTION TO TWO BPL HOUSEHOLDS AT PONMUDI              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : THIS PROJECT IS DESIGNED FOR CONSTRUCTING 560M OVERHEAD LINE FOR PROVIDING ELECTRIC POWER TO TWO HOUSEHOLDS AT PONMUDI              (iv). State : Kerala              (v). Category of the Project : Village Electricity              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 0.0672
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/KL/VELEC/51441/202021/10/202008/07/2021  17/03/2021  09/02/2021  04/11/2020   12/07/2021  06/06/2021  10/02/2021  09/02/2021   12/07/2021   15/07/2021 Thiruvananthapuram :19/07/2021Southern Circle, Kollam:
  23/07/2021 (Thiruvananthapuram)

Kerala:
23/07/2021
Kerala:
31/08/2021
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by State Government (Kerala) on:09/12/2021  
Query raised by Nodal Officer (Kerala) on:07/02/2022  
Query raised by Circle (Southern Circle, Kollam) on:08/11/2022  
NOTE:- Proposal is pending at DFO due to EDS raised by State Government .