TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/KL/VELEC/25488/2017              (ii). Name of Project for which Forest Land is required : Establishing UG Line under Total Electrification Project              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Establishing UG Line under Total Electrification Project              (iv). State : Kerala              (v). Category of the Project : Village Electricity              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 0.07
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/KL/VELEC/25488/201703/04/2017aa04/04/2017   12/04/2017 Thiruvananthapuram :12/04/2017Southern Circle, Kollam:
  24/04/2017 (Thiruvananthapuram)

Kerala:
20/09/2017
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Circle (Southern Circle, Kollam) on:18/08/2017  
Replied by DFO (Thiruvananthapuram) on:19/09/2017  
Query raised by DFO (Thiruvananthapuram) on:19/09/2017  
Replied by UA on :19/09/2017  
NOTE:- Proposal is pending at CF .