TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/KL/VELEC/23876/2017              (ii). Name of Project for which Forest Land is required : COMPLETE ELECTRIFICATION              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Constructing 40 Mtr single phase OH              (iv). File no. : GO(Rt) 200/2017/F & WLD              (v). State : Kerala              (vi). Category of the Project : Village Electricity              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.08001
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/KL/VELEC/23876/201701/02/201715/02/2017   15/02/2017   02/02/2017   14/02/2017 Thiruvananthapuram :25/02/2017Southern Circle, Kollam:
  09/03/2017 (Thiruvananthapuram)

Kerala:
25/03/2017
Kerala:
08/02/2018
Bangalore:
21/08/2019
27/05/2018
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
  
NOTE:- Stage-I Approval accorded by : State Government .