TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/KL/VELEC/23871/2017              (ii). Name of Project for which Forest Land is required : COMPLETE ELECTRIFICATION              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Constructing 200 Mtr single phase OH line              (iv). State : Kerala              (v). Category of the Project : Village Electricity              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 0.4
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/KL/VELEC/23871/201701/02/201718/02/2017  15/02/2017  08/02/2017  02/02/2017   15/02/2017  08/02/2017  07/02/2017   09/02/2017   14/02/2017 Thiruvananthapuram :25/02/2017
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by DFO (Thiruvananthapuram) on:30/07/2022  
NOTE:- Proposal is pending at DELISTED (due to non-reply of EDS by UA within 90 days) due to EDS raised by DELISTED .
Close(X)
Close(X)
Please wait ...