Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
State secretary
|
EDS
|
Nodal Officer
|
21/08/2019
|
Part 2 of district profile is found incomplete. DFO is advised to complete part 2
|
|
2
|
Nodal Officer
|
REPLY
|
State secretary
|
25/08/2019
|
The details were found complete
|
|
3
|
State secretary
|
EDS
|
Nodal Officer
|
25/08/2019
|
The proposal doesnt show up in processing tab of SG. The NIC expert has commented that the District profile in Part-II is incomplete
|
|
4
|
Nodal Officer
|
EDS
|
CF (Southern Circle, Kollam)
|
25/08/2019
|
The part-II of proposal is found incomplete. Please correct
|
|
5
|
CF (Southern Circle, Kollam)
|
EDS
|
DFO (Punalur)
|
25/08/2019
|
Please correct part-II of proposal
|
|
6
|
DFO (Punalur)
|
REPLY
|
CF (Southern Circle, Kollam)
|
25/08/2019
|
Updated district profile
|
|
7
|
CF (Southern Circle, Kollam)
|
REPLY
|
Nodal Officer
|
25/08/2019
|
The DFO has updated the district profile
|
|
8
|
Nodal Officer
|
REPLY
|
State secretary
|
25/08/2019
|
The DFO has updated the district profile as reported by the CCF
|
|
9
|
State secretary
|
EDS
|
Nodal Officer
|
25/08/2019
|
Still the problem persists
|
|
10
|
Nodal Officer
|
REPLY
|
State secretary
|
25/08/2019
|
I have tried updating the SI report. Please try if the page is active for updation at Sec side
|
|
11
|
State secretary
|
EDS
|
Nodal Officer
|
25/08/2019
|
Issue persists. Please coordinate with the NIC office
|
|
12
|
Nodal Officer
|
REPLY
|
State secretary
|
30/09/2019
|
Rectified
|
|
13
|
State secretary
|
EDS
|
Nodal Officer
|
09/12/2021
|
stage 1 apporval
|
|
14
|
Nodal Officer
|
EDS
|
CF (Southern Circle, Kollam)
|
08/02/2022
|
Compliance report
|
|
15
|
CF (Southern Circle, Kollam)
|
EDS
|
DFO (Punalur)
|
28/10/2022
|
Compliance report
|
|