Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Munnar)
|
EDS
|
User Agency (transgridsouth@gmail.com)
|
09/07/2020
|
Query for Upgradation of Pallivasal -Aluva 66kV feeder to 220 kV level 2 Ha
|
|
2
|
User Agency (transgridsouth@gmail.com)
|
REPLY
|
DFO (Munnar)
|
03/11/2020
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Munnar)
|
EDS
|
User Agency (transgridsouth@gmail.com)
|
13/05/2021
|
query No.2 addl details call for -reg
|
|
4
|
User Agency (transgridsouth@gmail.com)
|
REPLY
|
DFO (Munnar)
|
08/06/2021
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Kothamangalam)
|
EDS
|
User Agency (transgridsouth@gmail.com)
|
30/06/2021
|
Hard copies of the proposal not yet submitted. Hard copies and Land status details with ownership details of the entire project area which passes through this division should be submitted.
|
|
6
|
User Agency (transgridsouth@gmail.com)
|
REPLY
|
DFO (Kothamangalam)
|
19/10/2021
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Kothamangalam)
|
EDS
|
User Agency (transgridsouth@gmail.com)
|
21/10/2021
|
Project area details not yet submitted. Land status details with ownership details of the entire project area which passes through this division along with KML of the project area shall be submitted.
|
|
8
|
User Agency (transgridsouth@gmail.com)
|
REPLY
|
DFO (Kothamangalam)
|
17/11/2021
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Kothamangalam)
|
EDS
|
User Agency (transgridsouth@gmail.com)
|
29/11/2021
|
On verification of the submitted KML file of the above proposal, it is seen that about 450 meters of the existing line passes through the forest area in Kothamangalam Range under this division. Hence you are directed to submit the Right of Way of the already existing line for verification. If any widening of the line is proposed in the aforesaid area, details of forest land required for the same shall be reported. KML file showing the area proposed for widening also shall be submitted uploaded for verification.
|
|
10
|
User Agency (transgridsouth@gmail.com)
|
REPLY
|
DFO (Kothamangalam)
|
09/12/2021
|
The correction have been made as per the instruction received
|
|
11
|
DFO (Munnar)
|
EDS
|
User Agency (transgridsouth@gmail.com)
|
15/01/2022
|
Required details of compensatory Afforestation
|
|
12
|
User Agency (transgridsouth@gmail.com)
|
REPLY
|
DFO (Munnar)
|
11/05/2022
|
The correction have been made as per the instruction received
|
|
13
|
DFO (Munnar)
|
EDS
|
User Agency (transgridsouth@gmail.com)
|
14/10/2022
|
for non forest land
|
|
14
|
User Agency (transgridsouth@gmail.com)
|
REPLY
|
DFO (Munnar)
|
23/01/2023
|
The correction have been made as per the instruction received
|
|