Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
Regional Office
|
EDS
|
State secretary
|
01/04/2022
|
State Govt. has been requested vide letter dated 31-03-2022 to furnish the Certificate from Competent Authority about non-availability of non-forest land for the project, alternatives examined and comments of the CWLW since the proposed area falls within the Eco-Sensitive Zone of Periyar WLS.
|
|
2
|
State secretary
|
EDS
|
Nodal Officer
|
05/04/2022
|
please furnish the details urgently
|
|
3
|
Nodal Officer
|
EDS
|
CF (Southern Circle, Kollam)
|
11/05/2022
|
You are directed to furnish
1. Certificate from the District Collector about non availability of non forest land for the project.
2. At lease two alternative locations for this project need to be examined. & Reason for its rejection to be mentioned.
|
|
4
|
CF (Southern Circle, Kollam)
|
EDS
|
DFO (Ranni)
|
15/06/2022
|
Please rectify
|
|
5
|
DFO (Ranni)
|
REPLY
|
CF (Southern Circle, Kollam)
|
18/07/2022
|
The details called for are submitting herewith
|
|
6
|
CF (Southern Circle, Kollam)
|
REPLY
|
Nodal Officer
|
21/10/2022
|
Report uploaded
|
|
7
|
Nodal Officer
|
EDS
|
CF (Southern Circle, Kollam)
|
22/10/2022
|
The details sought by GoI MoEF&CC is forwarded herewith for remarks
|
|
8
|
CF (Southern Circle, Kollam)
|
EDS
|
DFO (Ranni)
|
26/10/2022
|
The details sought by GoI MoEF&CC is forwarded herewith for remarks
|
|
9
|
DFO (Ranni)
|
EDS
|
User Agency (shopampapta.pol@kerala.gov.in)
|
02/11/2022
|
Please furnish the details and upload via online and also submit the hard copy to O/o DFO Ranni
|
|
10
|
User Agency (shopampapta.pol@kerala.gov.in)
|
REPLY
|
DFO (Ranni)
|
24/05/2025
|
The correction have been made as per the instruction received
|
|
11
|
DFO (Ranni)
|
REPLY
|
CF (Southern Circle, Kollam)
|
04/08/2025
|
The inspection report of the alternative sites inspected for the police station is submitted
|
|
12
|
CF (Southern Circle, Kollam)
|
REPLY
|
Nodal Officer
|
04/08/2025
|
Reprot from DFO, Ranni is attached
|
|
13
|
Nodal Officer
|
REPLY
|
State secretary
|
25/08/2025
|
The details called for have been submitted by CCF, SC, Kollam.
The same is submitted for further necessary action
|
|
14
|
State secretary
|
EDS
|
Nodal Officer
|
30/08/2025
|
Details not seen uploaded
|
|
15
|
Nodal Officer
|
REPLY
|
State secretary
|
23/09/2025
|
The details are uploaded for further necessary action
|
|
16
|
State secretary
|
REPLY
|
Regional Office
|
03/10/2025
|
details attached herewith
|
|