Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
CF (Eastern Circle)
|
EDS
|
DFO (Mannarkad)
|
03/02/2020
|
You are not submitted Hard copy of this proposal.
|
|
2
|
DFO (Mannarkad)
|
REPLY
|
CF (Eastern Circle)
|
17/03/2020
|
Hard copies were submitted vide Divisional Forest Officer, Mannarkkad letter No D-5325/17 dated 03.02.2020. Copy of the same is uploaded herein.
|
|
3
|
Nodal Officer
|
EDS
|
CF (Eastern Circle)
|
26/05/2021
|
The proposal is returned for rectification.
|
|
4
|
CF (Eastern Circle)
|
EDS
|
DFO (Mannarkad)
|
08/06/2021
|
The proposal is returned for rectification
|
|
5
|
DFO (Mannarkad)
|
EDS
|
User Agency (cepshcltd@gmail.com)
|
18/06/2021
|
The proposal is returned for rectification.Please refer letter No.D5325/17 dated 16/06/2021 of Divisional Forest Officer, Mannarkkad
|
|
6
|
User Agency (cepshcltd@gmail.com)
|
REPLY
|
DFO (Mannarkad)
|
10/12/2021
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Mannarkad)
|
REPLY
|
CF (Eastern Circle)
|
03/01/2022
|
The application has been re uploaded as per the direction from APCCF & Nodal Officer,F(C) Act, TVM
|
|
8
|
CF (Eastern Circle)
|
REPLY
|
Nodal Officer
|
04/01/2022
|
The application has been re uploaded by DFO, as per the direction from APCCF & Nodal Officer,F(C) Act, TVM. The same is uploaded herewith.
|
|
9
|
Regional Office
|
EDS
|
State secretary
|
21/02/2022
|
Requested to furnish proper KML file and sketch of the proposed area and compliance report on the conditions stipulated for diversion of 1.15 ha of FL for construction of Small Hydel Project in Thuppanad at Meenavallam Falls, Mannarkkad Division, Palakkad vide letter dated 21-09-1999.
|
|
10
|
State secretary
|
EDS
|
Nodal Officer
|
04/03/2022
|
for furnishing the details sough by GOI
|
|
11
|
Nodal Officer
|
EDS
|
CF (Eastern Circle)
|
26/03/2022
|
1. Please upload proper kml file
2. Compliance report of conditions stipulated by GoI lr. No. FCA/11.2/KER/85/IP dt. 21.09.1999
|
|
12
|
CF (Eastern Circle)
|
EDS
|
DFO (Mannarkad)
|
28/03/2022
|
Please upload proper kml file 2. Compliance report of conditions stipulated by GoI lr. No. FCA/11.2/KER/85/IP dated. 21.09.1999
|
|
13
|
DFO (Mannarkad)
|
EDS
|
User Agency (cepshcltd@gmail.com)
|
18/04/2022
|
Please upload proper kml file 2. Compliance report of conditions stipulated by GoI lr. No. FCA/11.2/KER/85/IP dated. 21.09.1999
|
|
14
|
User Agency (cepshcltd@gmail.com)
|
REPLY
|
DFO (Mannarkad)
|
25/04/2022
|
The correction have been made as per the instruction received
|
|
15
|
DFO (Mannarkad)
|
REPLY
|
CF (Eastern Circle)
|
09/06/2022
|
Proper KML file/sketch has been uploaded by the user agency and remarks on the compliance report is also submitted.
|
|
16
|
CF (Eastern Circle)
|
REPLY
|
Nodal Officer
|
10/06/2022
|
Proper KML file/sketch has been uploaded by the user agency.
|
|
17
|
Nodal Officer
|
REPLY
|
State secretary
|
16/08/2022
|
Proper KML file uploaded and remarks on the compliance report submitted
|
|
18
|
State secretary
|
REPLY
|
Regional Office
|
06/09/2022
|
For further processing the proposal
|
|
19
|
RO/HQ
|
EDS
|
( ROBANG )
|
30/11/2022
|
EDS raised on 22.11.2022 and proposal returned back to IRO Bangalore
|
|
20
|
Regional Office
|
EDS
|
State secretary
|
30/11/2022
|
Requested to submit the plantation details and etc.
|
|
21
|
State secretary
|
EDS
|
Nodal Officer
|
19/12/2022
|
for furnishing the details sought by MoEF
|
|
22
|
Nodal Officer
|
EDS
|
CF (Eastern Circle)
|
27/01/2023
|
GoI Lr. No. 4-KLB1335/2022-BAN/1007 dated 29.11.2022 for submitting required details
|
|
23
|
CF (Eastern Circle)
|
EDS
|
DFO (Mannarkad)
|
03/02/2023
|
GoI Lr. No. 4-KLB1335/2022-BAN/1007 dated 29.11.2022 for submitting required details- You are directed to submit the required details urgently.
|
|