TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/KA/WIND/38582/2019              (ii). Name of Project for which Forest Land is required : Approval for already established 9 windmills of 8.55 MW Wind Power Project of MSPL Limited in Guddadarangavvanahalli village, Chitradurga Taluk and District              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : MSPL Limited 8.55 MW consisting of 9 Nos of wind mills at GR Halli village, Chitradurga for generation of wind power              (iv). State : Karnataka              (v). Category of the Project : Wind Power              (vi). Shape of forest land proposed to be diverted : Hybrid              (vii). Area of forest land proposed for diversion(in ha.): 11.71
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/KA/WIND/38582/201928/01/201916/02/2019   02/04/2019   10/05/2019   18/05/2019 Chitradurga :25/05/2019Bellary:
  08/03/2020 (Chitradurga)

Karnataka:
02/06/2020
Karnataka:
22/02/2022
Bangalore:
27/06/2022
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Bangalore) on:18/07/2022  
Query raised by State Government (Karnataka) on:21/12/2022  
Replied by Nodal Officer (Karnataka) on:19/12/2024  
Query raised by State Government (Karnataka) on:23/12/2024  
Replied by Nodal Officer (Karnataka) on:16/01/2025  
Query raised by Nodal Officer (Karnataka) on:08/07/2020  
Replied by Circle(Bellary) on:11/08/2020  
Query raised by Nodal Officer (Karnataka) on:21/09/2020  
Replied by Circle(Bellary) on:05/11/2020  
Query raised by Nodal Officer (Karnataka) on:11/12/2020  
Replied by Circle(Bellary) on:30/10/2021  
Query raised by Nodal Officer (Karnataka) on:24/01/2023  
Replied by Circle(Bellary) on:01/10/2024  
Query raised by Circle (Bellary) on:09/07/2020  
Replied by DFO (Chitradurga) on:30/07/2020  
Query raised by Circle (Bellary) on:22/09/2020  
Replied by DFO (Chitradurga) on:29/10/2020  
Query raised by Circle (Bellary) on:17/12/2020  
Replied by DFO (Chitradurga) on:11/08/2021  
Query raised by Circle (Bellary) on:14/09/2021  
Replied by DFO (Chitradurga) on:25/10/2021  
Query raised by Circle (Bellary) on:31/01/2023  
Replied by DFO (Chitradurga) on:04/07/2024  
Query raised by DFO (Chitradurga) on:06/08/2019  
Replied by UA on :31/08/2019  
Query raised by DFO (Chitradurga) on:05/12/2019  
Replied by UA on :03/03/2020  
Query raised by DFO (Chitradurga) on:09/10/2020  
Replied by UA on :14/10/2020  
Query raised by DFO (Chitradurga) on:04/01/2021  
Replied by UA on :18/02/2021  
Query raised by DFO (Chitradurga) on:17/09/2021  
Replied by UA on :16/10/2021  
Query raised by DFO (Chitradurga) on:06/05/2023  
Replied by UA on :12/02/2024  
Query raised by DFO (Chitradurga) on:20/03/2024  
Replied by UA on :01/06/2024  
NOTE:- Proposal is pending at State Government due to EDS raised by Regional Office .