Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Chitradurga)
|
EDS
|
User Agency (krishnavtar.goyal@mspllimited.com)
|
06/08/2019
|
• Sy No. 110 of G.R Halli, Chitradurga taluk, Chitradurga District is recorded as “Protected Forest” in column 9 in RTC.
Therefore as per Hon’ble Supreme Court order vide WP No.202/1995 the road length passing through this Sy No requires Forest Conservation approval.
|
|
2
|
User Agency (krishnavtar.goyal@mspllimited.com)
|
REPLY
|
DFO (Chitradurga)
|
31/08/2019
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Chitradurga)
|
EDS
|
User Agency (krishnavtar.goyal@mspllimited.com)
|
05/12/2019
|
• There is no CA suitable certificate uploaded by UA and CA Scheme not uploaded
|
|
4
|
User Agency (krishnavtar.goyal@mspllimited.com)
|
REPLY
|
DFO (Chitradurga)
|
03/03/2020
|
The correction have been made as per the instruction received
|
|
5
|
Nodal Officer
|
EDS
|
CF (Bellary)
|
08/07/2020
|
please submit information sought by this office letter attached below
|
|
6
|
CF (Bellary)
|
EDS
|
DFO (Chitradurga)
|
09/07/2020
|
In light of the EDS raised by the Nodal Officer vide his letter dated-08-07-2020, you are instructed to submit both hard copy in 3 ink signed sets and also through FC web portal. Treat this as most urgent.
|
|
7
|
DFO (Chitradurga)
|
REPLY
|
CF (Bellary)
|
30/07/2020
|
The following details have been uploaded Online and re-submitted the hard copies for your kind information and necessary action.
|
|
8
|
CF (Bellary)
|
REPLY
|
Nodal Officer
|
11/08/2020
|
The proposal may be considered as per the provisions of the FC Act, 1980.
|
|
9
|
Nodal Officer
|
EDS
|
CF (Bellary)
|
21/09/2020
|
please rectify the discrepancy and submit the corrected information
|
|
10
|
CF (Bellary)
|
EDS
|
DFO (Chitradurga)
|
22/09/2020
|
The details as sought for the Nodal Officer in the attached letter should be submitted.
|
|
11
|
DFO (Chitradurga)
|
EDS
|
User Agency (krishnavtar.goyal@mspllimited.com)
|
09/10/2020
|
It is stated in your reply that the Geo referenced map showing on the cadastral village map and mentioning the GPS readings forest extent 11 7 ha and CA extent 11 71 ha is rectified However there is change neither in Item B 24 nor in th Geo referenced map uploaded Item C iv of PART I Mention of CA extent in the reply is unwarranted
|
|
12
|
User Agency (krishnavtar.goyal@mspllimited.com)
|
REPLY
|
DFO (Chitradurga)
|
14/10/2020
|
The correction have been made as per the instruction received
|
|
13
|
DFO (Chitradurga)
|
REPLY
|
CF (Bellary)
|
29/10/2020
|
UA has corrected PART I Item No B 2 3 and B 2 4 and Uploaded Geo referenced Map in Item No C iv of PART I Geo referenced Map showing on the Cadastral village Map and mentioning the GPS readings Forest Extent 11 71 HA is rectified Annexure –1
|
|
14
|
CF (Bellary)
|
REPLY
|
Nodal Officer
|
05/11/2020
|
The proposal may be considered as per the provisions of the FC Act, 1980.
|
|
15
|
Nodal Officer
|
EDS
|
CF (Bellary)
|
11/12/2020
|
please corrected the information and resubmit
|
|
16
|
CF (Bellary)
|
EDS
|
DFO (Chitradurga)
|
17/12/2020
|
In light of the directions issued and additional information as sought for the by Nodal Officer should be submitted. The FC web portal link is forwarded herewith for necessary taking action.
|
|
17
|
DFO (Chitradurga)
|
EDS
|
User Agency (krishnavtar.goyal@mspllimited.com)
|
04/01/2021
|
Submit the information provided in B 2 4 with the corresponding information provided in other related items including maps
You are therefore required to rectify the above discrepancy in PART I of the proposal on FC web portal and submit the along with rectified Topo Map and Geo referenced Map in Nine copies 9 sets for taking further action in this regard
|
|
18
|
User Agency (krishnavtar.goyal@mspllimited.com)
|
REPLY
|
DFO (Chitradurga)
|
18/02/2021
|
The correction have been made as per the instruction received
|
|
19
|
DFO (Chitradurga)
|
REPLY
|
CF (Bellary)
|
11/08/2021
|
the undersigned visited the project site on 09-08-2021 verified the documents with reference to the proposal. The following details have been re-submitted the hard copies for your kind information and necessary action. UA has corrected PART-I Item No. B-2.4 and submitted Geo-referenced Map and Topo map
|
|
20
|
CF (Bellary)
|
EDS
|
DFO (Chitradurga)
|
14/09/2021
|
Resubmit the proposal as per the directions in the attached letter.
|
|
21
|
DFO (Chitradurga)
|
EDS
|
User Agency (krishnavtar.goyal@mspllimited.com)
|
17/09/2021
|
The user agency to include the above said excluded area as per the Chapter 8.1 of hand book of FC guidelines in Part-I web Portal and resubmit the proposal along with the relevant maps duly revised
|
|
22
|
User Agency (krishnavtar.goyal@mspllimited.com)
|
REPLY
|
DFO (Chitradurga)
|
16/10/2021
|
The correction have been made as per the instruction received
|
|
23
|
DFO (Chitradurga)
|
REPLY
|
CF (Bellary)
|
25/10/2021
|
The same has been received vide letter under Ref. (4) as below. (Copy enclosed).
“We have already included the 15 Meters wide Corridor for 33 KV Transmision lines and 8 Meters wide approach road to connect wind mill to wind mill in our Fc application. This proposal has already approved earlier 2 times and was also submitted
the proposal to PCCF office. The PCCf office has observed some minor typo-erroe and asked us to resubmit the proposal with necessary corrections. As per advise PCCF office, we have corrected the error and resubmitted the file”.
This proposal is already commissioned project and it is under running. Hence, hereby submitting the reply of
|
|
24
|
CF (Bellary)
|
REPLY
|
Nodal Officer
|
30/10/2021
|
EDS as sought for by your goodself is submitted herewith.
|
|
25
|
Regional Office
|
EDS
|
State secretary
|
18/07/2022
|
State Government has been requested vide letter dated 15-07-2022 to furnish the following viz., detailed report on violation, copy of Karnataka Food and Forest Department notification dated 21-04-1979, copy of Govt. of Karnataka letter No.RD41LGC dated 6-05-2002, copy of OM dated 6-7-2002 issued by DC, Chitradurga granting the 24 acres and 18 guntas, joint survey report of Revenue and Forest Department, Court orders in the connected matter, CCF Ballari order dated 13-08-2013 and ATR by the State Govt. on violation based on IRO letter dated 11-07-2017.
|
|
26
|
State secretary
|
EDS
|
Nodal Officer
|
21/12/2022
|
eds
|
|
27
|
Nodal Officer
|
EDS
|
CF (Bellary)
|
24/01/2023
|
Please submit the detais information
|
|
28
|
CF (Bellary)
|
EDS
|
DFO (Chitradurga)
|
31/01/2023
|
Submit point wise information/clarification
|
|
29
|
DFO (Chitradurga)
|
EDS
|
User Agency (krishnavtar.goyal@mspllimited.com)
|
06/05/2023
|
The Principal Chief Conservator of Forests Forest Conservation and Nodal Officer FCA Aranya Bhavan Bengaluru and the Chief Conservator of Forests Ballari Circle Ballari vide above references has directed to furnish the information documents required for further processing of the proposal
|
|
30
|
User Agency (krishnavtar.goyal@mspllimited.com)
|
REPLY
|
DFO (Chitradurga)
|
12/02/2024
|
The correction have been made as per the instruction received
|
|
31
|
DFO (Chitradurga)
|
EDS
|
User Agency (krishnavtar.goyal@mspllimited.com)
|
20/03/2024
|
you have not submitted original attested documents as per this office vide letter dated 20 02 23
|
|
32
|
User Agency (krishnavtar.goyal@mspllimited.com)
|
REPLY
|
DFO (Chitradurga)
|
01/06/2024
|
The correction have been made as per the instruction received
|
|
33
|
DFO (Chitradurga)
|
REPLY
|
CF (Bellary)
|
04/07/2024
|
UA has submitted information/documents
|
|
34
|
CF (Bellary)
|
REPLY
|
Nodal Officer
|
01/10/2024
|
Information submitted
|
|
35
|
Nodal Officer
|
REPLY
|
State secretary
|
19/12/2024
|
The reply is hereby attached for further necessary action
|
|
36
|
State secretary
|
EDS
|
Nodal Officer
|
23/12/2024
|
Please upload replay copy
|
|
37
|
Nodal Officer
|
REPLY
|
State secretary
|
16/01/2025
|
The copy of the proposal is hereby attached for further needful
|
|