Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
Nodal Officer
|
EDS
|
CF (Bellary)
|
08/07/2020
|
Please submit information sought by this office letter attached below
|
|
2
|
CF (Bellary)
|
EDS
|
DFO (Chitradurga)
|
09/07/2020
|
In light of the EDS raised by the Nodal Officer vide his letter dated-06-07-2020, you are instructed to submit both hard copy in 3 ink signed sets and also through FC web portal. Treat this as most urgent.
|
|
3
|
DFO (Chitradurga)
|
REPLY
|
CF (Bellary)
|
30/07/2020
|
The following details have been uploaded Online and re-submitted the hard copies for your kind information and necessary action
|
|
4
|
CF (Bellary)
|
REPLY
|
Nodal Officer
|
11/08/2020
|
The proposal may be considered as per the provisions of the FC Act, 1980.
|
|
5
|
Regional Office
|
EDS
|
State secretary
|
20/04/2022
|
IRO vide letter dated 20-04-2022 requested the State Government to submit the detailed violation report, including officers involved, copies of Government of Karnataka notification dated 21-04-1979, copy of Government of Karnataka order No RD41LGC dated 06-05-2002, OM dated 06-07-2022 issued by DC, Chitradurga granting 24 acres and 18 gunta land on lease basis to KREDL, joint survey report of Revenue Department and Forest Department of the 2002, Hon’ble Court orders, CCF, Ballari order dated 25-09-2021 and ATR by State Government on violation.
|
|
6
|
State secretary
|
EDS
|
Nodal Officer
|
09/05/2022
|
eds
|
|
7
|
Nodal Officer
|
EDS
|
CF (Bellary)
|
23/05/2022
|
please submit the report sought by GOI
|
|
8
|
CF (Bellary)
|
EDS
|
DFO (Chitradurga)
|
06/06/2022
|
Submit report immediately
|
|
9
|
DFO (Chitradurga)
|
EDS
|
User Agency (chidanand.n@rmml.in)
|
11/07/2022
|
The Principal Chief Conservator of Forests Head of Forest Force Aranya Bhavan Bengaluru letter dated 21 05 2022 and the Chief Conservator of Forests Ballari Circle Ballari dated 20 06 2022 has directed to furnish the information/documents required for further processing of the proposal
|
|
10
|
User Agency (chidanand.n@rmml.in)
|
REPLY
|
DFO (Chitradurga)
|
30/11/2023
|
The correction have been made as per the instruction received
|
|
11
|
DFO (Chitradurga)
|
REPLY
|
CF (Bellary)
|
02/12/2023
|
RMML submitted an online application No FP KA WIND 38530 2019 on 30 01 2019 seeking diversion of forest land involved in the above mentioned wind power project the sister concern MSPL also submitted a similar FC Proposal No FP KA WIND 38582 2019
This proposal is already commissioned project and it is under running Hence hereby submitting the report as above for your kind perusal and further needful
|
|
12
|
CF (Bellary)
|
REPLY
|
Nodal Officer
|
13/12/2023
|
Additional Information Submitted.
|
|
13
|
Nodal Officer
|
EDS
|
CF (Bellary)
|
03/04/2024
|
the reply submited by the DCF Chitradurga is found to be incomplete hence Please submit the reply as per GOI letter dated 11-01-2017 in EDS query poin t no 8
|
|
14
|
CF (Bellary)
|
EDS
|
DFO (Chitradurga)
|
15/06/2024
|
Submit sought information
|
|
15
|
DFO (Chitradurga)
|
REPLY
|
CF (Bellary)
|
04/07/2024
|
In this regard verified the documents with reference to the proposal Therefore I am herewith submitting the following information for your kind information and necessary action
|
|
16
|
CF (Bellary)
|
REPLY
|
Nodal Officer
|
01/10/2024
|
Information submitted
|
|
17
|
Nodal Officer
|
REPLY
|
State secretary
|
19/12/2024
|
The reply is hereby attached for further needful
|
|