Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Bangalore Urban)
|
EDS
|
User Agency (eek1@bwssb.gov.in)
|
11/01/2022
|
Please Change the drawings and upload as per the new location suggested during inspection. please check the letter
|
|
2
|
User Agency (eek1@bwssb.gov.in)
|
REPLY
|
DFO (Bangalore Urban)
|
12/02/2022
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Bangalore Urban)
|
EDS
|
User Agency (eek1@bwssb.gov.in)
|
03/06/2022
|
Alternate CA land to be identified and changes to be made in FORM-A and submit
|
|
4
|
User Agency (eek1@bwssb.gov.in)
|
REPLY
|
DFO (Bangalore Urban)
|
03/01/2023
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Bangalore Urban)
|
EDS
|
User Agency (eek1@bwssb.gov.in)
|
30/03/2023
|
Plese update the new CA aea details
|
|
6
|
User Agency (eek1@bwssb.gov.in)
|
REPLY
|
DFO (Bangalore Urban)
|
24/04/2023
|
The correction have been made as per the instruction received
|
|
7
|
Regional Office
|
EDS
|
State secretary
|
01/11/2023
|
Requested vide letter dated 1-11-2023 to explore the possibility of re-diversion of forest land from the BMRCL and clarify whether the DFL identified is in addition to NFL identified already.
|
|
8
|
State secretary
|
EDS
|
Nodal Officer
|
08/11/2023
|
eds
|
|
9
|
Nodal Officer
|
EDS
|
CF (Bangalore)
|
27/11/2023
|
you are directed to obtain the required information from the User Agency through jurisdictional Deputy Conservator of Forests, verify and then submit
|
|
10
|
CF (Bangalore)
|
EDS
|
DFO (Bangalore Urban)
|
28/11/2023
|
As per direction of PCCF, FC latter dated 08-11-2023 you are hereby directed to obtain information for the points raised by Govt of India letter dated 01-11-2023 from the user Agencey and submit at the earliest.
|
|
11
|
DFO (Bangalore Urban)
|
EDS
|
User Agency (eek1@bwssb.gov.in)
|
28/11/2023
|
User Agency is informed to submit the clarification sought by MoEF
|
|
12
|
User Agency (eek1@bwssb.gov.in)
|
REPLY
|
DFO (Bangalore Urban)
|
28/11/2023
|
The correction have been made as per the instruction received
|
|
13
|
DFO (Bangalore Urban)
|
REPLY
|
CF (Bangalore)
|
28/11/2023
|
The User Agency has submitted the clarification sought by Moef. The same is forwarded for further necessary action.
|
|
14
|
CF (Bangalore)
|
REPLY
|
Nodal Officer
|
04/12/2023
|
As per direction of your office letter dated 08-11-2023, information has been obtained by the user Agencey and has been submitted by DCF, Bengaluru Urban, while enclosing the same has been forwarded for kind perusal and necessary action
|
|
15
|
Nodal Officer
|
REPLY
|
State secretary
|
20/12/2023
|
EDS reply submited for your kind information.
|
|
16
|
State secretary
|
REPLY
|
Regional Office
|
26/12/2023
|
eds
|
|
17
|
Regional Office
|
EDS
|
State secretary
|
17/01/2024
|
State Govt. has been requested vide letter dtd. 12.01.2024 to provide the degraded forest land which is twice in extent for the shortfall along with revised CA scheme, KML file and MAPs.
|
|
18
|
State secretary
|
EDS
|
Nodal Officer
|
07/02/2024
|
?????? ???????? ??????? ???????? ??????????? ???????
??? ??????.
|
|
19
|
Nodal Officer
|
EDS
|
CF (Bangalore)
|
08/02/2024
|
Submit reply to EDS
|
|
20
|
CF (Bangalore)
|
EDS
|
DFO (Bangalore Urban)
|
08/02/2024
|
Submit reply to EDS
|
|
21
|
DFO (Bangalore Urban)
|
REPLY
|
CF (Bangalore)
|
27/03/2024
|
All necessary documents are uploaded for further needful action
|
|
22
|
CF (Bangalore)
|
REPLY
|
Nodal Officer
|
27/03/2024
|
submitted for further action
|
|
23
|
Nodal Officer
|
REPLY
|
State secretary
|
27/03/2024
|
Additional information sought by GoI. Reply enclosed
|
|
24
|
State secretary
|
REPLY
|
Regional Office
|
28/03/2024
|
EDS
|
|