Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
Nodal Officer
|
EDS
|
CF (Kanara)
|
18/08/2021
|
EDS
|
|
2
|
CF (Kanara)
|
EDS
|
DFO (Dandeli Wildlife)
|
25/08/2021
|
EDS
|
|
3
|
DFO (Dandeli Wildlife)
|
EDS
|
User Agency (eekpdkhanapurf@gmail.com)
|
18/09/2021
|
Intimation to submit proposal for wildlife clearance for the proposed Kadagarni - Ulavi drinking water project by KNNL, Belgaum.
|
|
4
|
User Agency (eekpdkhanapurf@gmail.com)
|
REPLY
|
DFO (Dandeli Wildlife)
|
09/03/2022
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Dandeli Wildlife)
|
REPLY
|
CF (Kanara)
|
17/03/2022
|
Reply for EDS
|
|
6
|
CF (Kanara)
|
REPLY
|
Nodal Officer
|
12/05/2022
|
eds
|
|
7
|
Regional Office
|
EDS
|
State secretary
|
13/02/2023
|
State Government has been requested vide IRO letter dated 13-02-2023 to verify whether any submergence of forest land is involved and also whether any power lines are to be drawn through forest area and if so to include the same in the proposal. It is also requested to furnish the recommendation of Standing Committee of NBWL, since the proposed area is part of Anshi-Dandeli National Park.
|
|
8
|
State secretary
|
EDS
|
Nodal Officer
|
23/02/2023
|
eds
|
|
9
|
Nodal Officer
|
EDS
|
CF (Kanara)
|
02/03/2023
|
EDS
|
|
10
|
CF (Kanara)
|
EDS
|
DFO (Dandeli Wildlife)
|
15/03/2023
|
EDS
|
|
11
|
DFO (Dandeli Wildlife)
|
EDS
|
User Agency (eekpdkhanapurf@gmail.com)
|
20/03/2023
|
Upload revised proposal as per MOEF guidelines
|
|
12
|
User Agency (eekpdkhanapurf@gmail.com)
|
REPLY
|
DFO (Dandeli Wildlife)
|
04/12/2024
|
The correction have been made as per the instruction received
|
|
13
|
DFO (Dandeli Wildlife)
|
EDS
|
User Agency (eekpdkhanapurf@gmail.com)
|
30/01/2025
|
As per the site inspection dated 28/01/2025, one more component is required for this project i.e in-take canal. The in-take canal component of this project should be revised and added by the user agency.
|
|
14
|
User Agency (eekpdkhanapurf@gmail.com)
|
REPLY
|
DFO (Dandeli Wildlife)
|
04/02/2025
|
The correction have been made as per the instruction received
|
|
15
|
DFO (Dandeli Wildlife)
|
REPLY
|
CF (Kanara)
|
14/02/2025
|
Reply submitted
|
|
16
|
CF (Kanara)
|
REPLY
|
Nodal Officer
|
28/02/2025
|
EDS Reply
|
|