Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Kudremukh)
|
EDS
|
User Agency (eechikkamagaluru@kridl.net)
|
06/06/2020
|
For this proposal it is noticed that certain crucial information required for processing under FC Act has not been provided completely.it is requested to provide the required information online at the earliest for further processing of the proposal.
|
|
2
|
User Agency (eechikkamagaluru@kridl.net)
|
REPLY
|
DFO (Kudremukh)
|
19/10/2020
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Kudremukh)
|
EDS
|
User Agency (eechikkamagaluru@kridl.net)
|
01/03/2021
|
Regarding Submission of Compensatory Afforestation land details
|
|
4
|
User Agency (eechikkamagaluru@kridl.net)
|
REPLY
|
DFO (Kudremukh)
|
28/06/2021
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Kudremukh)
|
EDS
|
User Agency (eechikkamagaluru@kridl.net)
|
28/07/2021
|
Regarding Submission of Site Suitability Certificate
|
|
6
|
User Agency (eechikkamagaluru@kridl.net)
|
REPLY
|
DFO (Kudremukh)
|
30/09/2021
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Kudremukh)
|
EDS
|
User Agency (eechikkamagaluru@kridl.net)
|
09/11/2021
|
Directed to submit clarification/information sought by GOK
|
|
8
|
User Agency (eechikkamagaluru@kridl.net)
|
REPLY
|
DFO (Kudremukh)
|
04/12/2021
|
The correction have been made as per the instruction received
|
|