TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/KA/WATER/31233/2018              (ii). Name of Project for which Forest Land is required : Providing Water supply scheme to Hassan city              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : 0.9894 ha of forest land is required for laying of 1118 mm dia M s gravity feeder pipe line to supply water for Hassan city.              (iv). File no. : No.4-KRB1180/2019-BAN              (v). State : Karnataka              (vi). Category of the Project : Drinking Water              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.9894
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/KA/WATER/31233/201808/01/201823/05/2018  19/03/2018  25/01/2018   26/06/2018  10/05/2018  13/03/2018   17/07/2018   28/07/2018 Hassan :31/07/2018Hassan:
  25/10/2018 (Hassan)

Karnataka:
02/11/2018
Karnataka:
29/11/2018
Bangalore:
04/02/2019
26/06/2019
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Bangalore) on:08/03/2019  
Replied by State Government(Karnataka) on:21/06/2019  
Query raised by State Government (Karnataka) on:27/03/2019  
Replied by Nodal Officer (Karnataka) on:19/06/2019  
Query raised by Nodal Officer (Karnataka) on:04/04/2019  
Replied by Circle(Hassan) on:13/06/2019  
Query raised by Circle (Hassan) on:24/04/2019  
Replied by DFO (Hassan) on:18/05/2019  
Query raised by Circle (Hassan) on:07/06/2019  
Replied by DFO (Hassan) on:12/06/2019  
NOTE:- Stage-I Approval accorded by : Regional Office .