TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/KA/WATER/26128/2017              (ii). Name of Project for which Forest Land is required : Contraction of vented dam in providing water supply scheme to Kollur village, Kundapur forest division in favor of Executive Officer Sri Mookambika Temple Kollur              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of 0.352 Ha of forest land in Sy No.56 of Kollur village Kundapur Tq. Udupi Dist, Kundapur forest division for construction of vented dam in providing water supply scheme to Kollur village, Kundapur forest division in favor of Executive Officer Sri Mookambika Temple Kollur              (iv). File no. : F.No.4-KRB1141/2018-BAN              (v). State : Karnataka              (vi). Category of the Project : Drinking Water              (vii). Shape of forest land proposed to be diverted : Non Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.352
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/KA/WATER/26128/201711/05/201727/05/2017   21/07/2017   21/07/2017   28/07/2017 Kundapur :01/08/2017Mangalore:
  26/08/2017 (Kundapur)

Karnataka:
30/08/2017
Karnataka:
07/12/2017
Bangalore:
02/02/2018
11/12/2018
By :Regional Office
Karnataka
19/03/2021
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Bangalore) on:16/03/2018  
Replied by State Government(Karnataka) on:04/12/2018  
Query raised by State Government (Karnataka) on:27/04/2018  
Replied by Nodal Officer (Karnataka) on:28/06/2018  
Query raised by State Government (Karnataka) on:26/10/2018  
Replied by Nodal Officer (Karnataka) on:26/10/2018  
Query raised by Nodal Officer (Karnataka) on:30/04/2018  
Replied by Circle(Mangalore) on:04/06/2018  
D. Essential Details Sought History (Stage-II)
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by Regional Office (Bangalore) on:23/03/2021  
Query raised by State Government (Karnataka) on:20/04/2021  
Query raised by Nodal Officer on:27/04/2021  
NOTE:- Proposal is pending at User Agency due to EDS raised by RO for Stage-II .