| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
DFO (Belgaum)
|
EDS
|
User Agency (eekpdkhanapurf@gmail.com)
|
06/07/2022
|
demarcation is not done by the user agency
|
|
|
2
|
User Agency (eekpdkhanapurf@gmail.com)
|
REPLY
|
DFO (Belgaum)
|
10/10/2022
|
The correction have been made as per the instruction received
|
|
|
3
|
DFO (Belgaum)
|
EDS
|
User Agency (eekpdkhanapurf@gmail.com)
|
25/10/2022
|
1. Submit complete enumeration list of trees to be felled.
2. Submit Detailed Project Report.
3 .Project area comes under ECO Class 1 VDF, NPV payable accordingly by user agency.
4.GPS coordinates not matching in some points on ground, the same should be rectified.
5. The boundary should be demarcated completely on the ground.
|
|
|
4
|
User Agency (eekpdkhanapurf@gmail.com)
|
REPLY
|
DFO (Belgaum)
|
23/11/2022
|
The correction have been made as per the instruction received
|
|
|
5
|
DFO (Belgaum)
|
EDS
|
User Agency (eekpdkhanapurf@gmail.com)
|
12/12/2022
|
Please submit compliance to the observations made in the enclosed letter
|
|
|
6
|
User Agency (eekpdkhanapurf@gmail.com)
|
REPLY
|
DFO (Belgaum)
|
17/12/2022
|
The correction have been made as per the instruction received
|
|
|
7
|
DFO (Belgaum)
|
EDS
|
User Agency (eekpdkhanapurf@gmail.com)
|
21/12/2022
|
The ACF Khanapur in his letter Dtd 19-12-2022 has submitted that Kalanayakanahatti Sy.No. 133 is privated land. Therefore it is requested to rectify the same
|
|
|
8
|
User Agency (eekpdkhanapurf@gmail.com)
|
REPLY
|
DFO (Belgaum)
|
21/12/2022
|
The correction have been made as per the instruction received
|
|
|
9
|
CF (Belgaum)
|
EDS
|
DFO (Belgaum)
|
26/12/2022
|
EXECUTIVE ENGINEER KNNL KALASA PROJECT DIVISON BELAGAVI
|
|
|
10
|
DFO (Belgaum)
|
REPLY
|
CF (Belgaum)
|
26/12/2022
|
All details have been updated and submitted for further action
|
|
|
11
|
Regional Office
|
EDS
|
State secretary
|
05/01/2023
|
State Govt has been requested vide letter dated 5-1-2023 to process the proposal as per FC Rule 2022, to provide details of alternatives examined, to provide clarification on CA, recommendation and mitigation measures of CWLW, CB ratio as per FC Guidelines etc.
|
|
|
12
|
State secretary
|
EDS
|
Nodal Officer
|
09/01/2023
|
eds
|
|
|
13
|
Nodal Officer
|
EDS
|
CF (Belgaum)
|
10/01/2023
|
please obtain the information sough by GOI
|
|
|
14
|
CF (Belgaum)
|
EDS
|
DFO (Belgaum)
|
10/01/2023
|
please obtain the information sough by GOI
|
|
|
15
|
DFO (Belgaum)
|
EDS
|
User Agency (eekpdkhanapurf@gmail.com)
|
10/01/2023
|
Comply all the observations made by the Govt.of India, MoEF & CC letter Dated 5-1-2023
|
|
|
16
|
User Agency (eekpdkhanapurf@gmail.com)
|
REPLY
|
DFO (Belgaum)
|
12/01/2023
|
The correction have been made as per the instruction received
|
|
|
17
|
DFO (Belgaum)
|
EDS
|
User Agency (eekpdkhanapurf@gmail.com)
|
12/01/2023
|
Submit Compliance to all observation made by the IRO MoEFC Bangalore letter no 1165 dtd 05-01-2023 with hard copy in 8 sets with Signature.
|
|
|
18
|
User Agency (eekpdkhanapurf@gmail.com)
|
REPLY
|
DFO (Belgaum)
|
13/01/2023
|
The correction have been made as per the instruction received
|
|
|
19
|
DFO (Belgaum)
|
REPLY
|
CF (Belgaum)
|
14/01/2023
|
Observations are complied and re-submitted
|
|
|
20
|
CF (Belgaum)
|
REPLY
|
Nodal Officer
|
14/01/2023
|
Reply to EDS dated 10-01-2023
|
|
|
21
|
Nodal Officer
|
REPLY
|
State secretary
|
14/01/2023
|
the reply obtained from field officers is hereby enclosed for further needfull
|
|
|
22
|
State secretary
|
REPLY
|
Regional Office
|
15/01/2023
|
clarification and information on 8 points viz psc recommendation etc.,
|
|
|
23
|
Regional Office
|
EDS
|
State secretary
|
30/01/2023
|
State Govt. has been requested vide IRO letter dated 30-1-2023 to furnish clarification, information on exploring the possibility for strengthening the CA scheme from the perspective of silvicultural requirements, incorporation of suitable mitigation measures by CWLW since the project is falling in the Tiger corridor and complying with the requirement prescribed under MoEFCC guidelines dated 17-5-2022 in such cases and etc.
|
|
|
24
|
State secretary
|
EDS
|
Nodal Officer
|
31/01/2023
|
eds
|
|
|
25
|
Nodal Officer
|
EDS
|
CF (Belgaum)
|
10/02/2023
|
please submit the details sough tby GOI
|
|
|
26
|
CF (Belgaum)
|
EDS
|
DFO (Belgaum)
|
27/02/2023
|
please submit the details sough tby GOI
|
|
|
27
|
DFO (Belgaum)
|
EDS
|
User Agency (eekpdkhanapurf@gmail.com)
|
03/04/2023
|
Please furnish compliance to the observations made by the Govt. of India in letter Dated 30-1-2023 copy enclosed
|
|
|
28
|
User Agency (eekpdkhanapurf@gmail.com)
|
REPLY
|
DFO (Belgaum)
|
31/05/2023
|
The correction have been made as per the instruction received
|
|
|
29
|
DFO (Belgaum)
|
REPLY
|
CF (Belgaum)
|
15/07/2023
|
Compliance to EDS is submitted for kind perusal
|
|
|
30
|
CF (Belgaum)
|
REPLY
|
Nodal Officer
|
27/07/2023
|
submitted to Compliance for EDS for kind perusal
|
|
|
31
|
Nodal Officer
|
REPLY
|
State secretary
|
22/08/2023
|
The information sought by GOI is hereby enclosed for further necessary action
|
|
|
32
|
State secretary
|
REPLY
|
Regional Office
|
31/08/2023
|
EDS
|
|
|
33
|
Regional Office
|
EDS
|
State secretary
|
07/09/2023
|
Comments and reviews on the issues raised by Secretary, Water resource etc.
|
|
|
34
|
State secretary
|
REPLY
|
Regional Office
|
12/09/2023
|
EDS
|
|
|
35
|
Regional Office
|
EDS
|
State secretary
|
29/09/2023
|
Requested to submit the reply to this office earlier EDS letter dated 07.09.2023.
|
|
|
36
|
State secretary
|
EDS
|
Nodal Officer
|
03/10/2023
|
eds
|
|
|
37
|
Nodal Officer
|
EDS
|
CF (Belgaum)
|
06/10/2023
|
please obtain the report from DCF and UA
|
|
|
38
|
CF (Belgaum)
|
EDS
|
DFO (Belgaum)
|
07/10/2023
|
please obtain the report from DCF and UA
|
|
|
39
|
DFO (Belgaum)
|
EDS
|
User Agency (eekpdkhanapurf@gmail.com)
|
07/10/2023
|
EDS
|
|
|
40
|
User Agency (eekpdkhanapurf@gmail.com)
|
REPLY
|
DFO (Belgaum)
|
25/09/2025
|
The correction have been made as per the instruction received
|
|
|
41
|
DFO (Belgaum)
|
REPLY
|
CF (Belgaum)
|
18/10/2025
|
Compliance on EDS
|
|