| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
CF (Mangalore)
|
EDS
|
DFO (Mangalore)
|
04/10/2017
|
Verify and submit the balance levies pertaining to earlier clearances in favour of User agency and accordingly send with remarks
|
|
|
2
|
DFO (Mangalore)
|
EDS
|
User Agency (jemescomaranthodu@rediffmail.com)
|
29/01/2018
|
Your online proposal sent back to you as per letter dated 29-1-2018 enclosed.
|
|
|
3
|
User Agency (jemescomaranthodu@rediffmail.com)
|
REPLY
|
DFO (Mangalore)
|
21/02/2019
|
The correction have been made as per the instruction received
|
|
|
4
|
DFO (Mangalore)
|
EDS
|
User Agency (jemescomaranthodu@rediffmail.com)
|
07/03/2019
|
Verify and submit levies pertaining to Hemala Project in favour of MESCOM Sullia as per letter dated 7-3-2019
|
|
|
5
|
User Agency (jemescomaranthodu@rediffmail.com)
|
REPLY
|
DFO (Mangalore)
|
04/07/2019
|
The correction have been made as per the instruction received
|
|
|
6
|
DFO (Mangalore)
|
REPLY
|
CF (Mangalore)
|
18/07/2019
|
Detail report attached.
|
|
|
7
|
State secretary
|
EDS
|
Nodal Officer
|
13/02/2020
|
justification for 0.80 ha
min 3 alternatives
|
|
|
8
|
Nodal Officer
|
EDS
|
CF (Mangalore)
|
07/03/2020
|
submit the gok required information as on 07-02-2020
|
|
|
9
|
CF (Mangalore)
|
EDS
|
DFO (Mangalore)
|
18/03/2020
|
as per directions of nodal officer
|
|
|
10
|
DFO (Mangalore)
|
EDS
|
User Agency (jemescomaranthodu@rediffmail.com)
|
18/03/2020
|
As per instructed by nodal officer FC
|
|
|
11
|
User Agency (jemescomaranthodu@rediffmail.com)
|
REPLY
|
DFO (Mangalore)
|
29/05/2020
|
The correction have been made as per the instruction received
|
|
|
12
|
DFO (Mangalore)
|
REPLY
|
CF (Mangalore)
|
29/05/2020
|
Letter Enclosed
|
|
|
13
|
CF (Mangalore)
|
REPLY
|
Nodal Officer
|
30/05/2020
|
Information for enclosed.
|
|
|
14
|
Nodal Officer
|
REPLY
|
State secretary
|
18/06/2020
|
information received from field officers. the same has been sent to GOK for further action
|
|