TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/KA/TRANS/23117/2016              (ii). Name of Project for which Forest Land is required : For laying / Establishment of 11 KV H/T AB Bunch Cable transmission line from Sulkeri Mogru to Panjala & Mallige enclosure passing through Naravi RF, Karkala Wildlife Division, Belthangady Taluk, D.K. District in favour of the Assistant Executive Engineer (Ele) MESCOM O&M Sub Division, Belthangady              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of 0.0647 ha. of Forest land in Sy.No.64 of Sulkeri Mogru Village, Naravi RF, Belthangady Wildlife Range, Karkala Wildlife Division, D.K. District for laying / establishment of 11 KV transmission line (H/T AB Bunch Cable over on poles along with existing Road) from Sulkeri Mogru to Panjala              (iv). File no. : F.No.4-KRB1150/2018-BAN              (v). State : Karnataka              (vi). Category of the Project : Transmission Line              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.0647
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/KA/TRANS/23117/201617/12/201619/01/2017   03/03/2017   03/03/2017   25/07/2017 Kudremukh :25/07/2017Mangalore:
  28/08/2017 (Kudremukh)

Karnataka:
30/08/2017
Karnataka:
16/12/2017
Bangalore:
01/03/2025
17/03/2025
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by State Government (Karnataka) on:12/03/2018  
Replied by Nodal Officer (Karnataka) on:14/03/2018  
Query raised by State Government (Karnataka) on:13/10/2020  
Replied by Nodal Officer (Karnataka) on:16/10/2020  
Query raised by State Government (Karnataka) on:07/07/2021  
Replied by Nodal Officer (Karnataka) on:13/07/2021  
Query raised by State Government (Karnataka) on:14/02/2022  
Replied by Nodal Officer (Karnataka) on:19/02/2022  
Query raised by State Government (Karnataka) on:18/03/2023  
Replied by Nodal Officer (Karnataka) on:20/03/2023  
Query raised by State Government (Karnataka) on:14/09/2023  
Replied by Nodal Officer (Karnataka) on:26/09/2023  
Query raised by State Government (Karnataka) on:17/12/2024  
Replied by Nodal Officer (Karnataka) on:20/01/2025  
Query raised by Nodal Officer (Karnataka) on:18/12/2024  
Replied by Circle(Mangalore) on:23/12/2024  
Query raised by Circle (Mangalore) on:18/12/2024  
Replied by DFO (Kudremukh) on:23/12/2024  
NOTE:- Stage-I Approval accorded by : Regional Office .