Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
CF (Belgaum)
|
EDS
|
DFO (Bagalkot)
|
09/04/2018
|
Short comings listed in letter dated 09-04-2018 shall be complied for further consideration of the proposal.
|
|
2
|
DFO (Bagalkot)
|
EDS
|
User Agency (eeemwdbagalkot@gmail.com)
|
19/06/2018
|
Pls upload above letter observations
|
|
3
|
User Agency (eeemwdbagalkot@gmail.com)
|
REPLY
|
DFO (Bagalkot)
|
12/09/2018
|
The correction have been made as per the instruction received
|
|
4
|
DFO (Bagalkot)
|
EDS
|
User Agency (eeemwdbagalkot@gmail.com)
|
04/10/2018
|
CA Land Details and Model Estimate copy uploaded as pe instruction
|
|
5
|
User Agency (eeemwdbagalkot@gmail.com)
|
REPLY
|
DFO (Bagalkot)
|
04/10/2018
|
The correction have been made as per the instruction received
|
|
6
|
DFO (Bagalkot)
|
REPLY
|
CF (Belgaum)
|
04/10/2018
|
Upload CA land & Estimation details as per your instructions.
|
|
7
|
Nodal Officer
|
EDS
|
CF (Belgaum)
|
03/12/2018
|
Since the hard copy of the proposal Part-II & III is yet to be received in this office is not in a position to submit to Government of Karnatata. Hence online link sent back to Circle.
|
|
8
|
CF (Belgaum)
|
REPLY
|
Nodal Officer
|
22/12/2018
|
proposal already submitted as per this office letter dated:31-10-2018 in hard copy 4 set
|
|
9
|
State secretary
|
EDS
|
Nodal Officer
|
20/02/2019
|
FURNISH FRA COMPLIANCE
|
|
10
|
Nodal Officer
|
REPLY
|
State secretary
|
27/03/2019
|
In this connection, it is to submit that the FRA compliance certificate (Form-I)
issued by the Deputy Commissioner, Bagalkote District vide letter No. LND/CR167/18-19 dated 08-08-2018 has already been uploaded in Additional Information
Details in PRAT-I.
|
|
11
|
Regional Office
|
EDS
|
State secretary
|
20/06/2019
|
Site suitability certificate and CA details
|
|
12
|
State secretary
|
EDS
|
Nodal Officer
|
29/10/2020
|
SITE SUITABILITY AND CA DETAILS.
|
|
13
|
Nodal Officer
|
REPLY
|
State secretary
|
20/11/2020
|
the CA site suitability certificate and a detailed CA scheme are submitted for kind perusal
|
|
14
|
State secretary
|
EDS
|
Nodal Officer
|
10/12/2020
|
please furnish site suitability certificate and upload all documents online.
|
|
15
|
Nodal Officer
|
REPLY
|
State secretary
|
10/12/2020
|
As per your direction site suitability certificate and CA scheme details are uploaded here for information
|
|
16
|
State secretary
|
REPLY
|
Regional Office
|
01/01/2021
|
INFORMATION TO THE EDS RAISED BY MOEF VIDE LETTERS DATED 19-06-2029 AND 10-09-2020
|
|
17
|
Regional Office
|
EDS
|
State secretary
|
08/02/2021
|
Detailed report on violation.
|
|
18
|
State secretary
|
EDS
|
Nodal Officer
|
23/02/2021
|
VIOLATION REPORT
|
|
19
|
Nodal Officer
|
EDS
|
CF (Belgaum)
|
12/03/2021
|
please obtain the information form concerned DCF as the information sought by GOI
|
|
20
|
CF (Belgaum)
|
EDS
|
DFO (Bagalkot)
|
01/04/2021
|
please obtain the information form concerned UA as the information sought by GOI
|
|
21
|
DFO (Bagalkot)
|
REPLY
|
CF (Belgaum)
|
17/07/2021
|
U/A is violated the FC Act
|
|
22
|
CF (Belgaum)
|
EDS
|
DFO (Bagalkot)
|
04/08/2021
|
please obtain the information form concerned DCF as the information sought by GOI
|
|
23
|
DFO (Bagalkot)
|
EDS
|
User Agency (eeemwdbagalkot@gmail.com)
|
19/08/2021
|
As per direction of PCCF (FC) submit all responsible officers names of F(C)
|
|
24
|
User Agency (eeemwdbagalkot@gmail.com)
|
REPLY
|
DFO (Bagalkot)
|
14/09/2021
|
The correction have been made as per the instruction received
|
|
25
|
DFO (Bagalkot)
|
REPLY
|
CF (Belgaum)
|
04/11/2021
|
Sir Report Submitted here for FC Act violation reg
|
|
26
|
CF (Belgaum)
|
EDS
|
DFO (Bagalkot)
|
06/11/2021
|
please obtain the information form concerned DCF as the information sought by GOI
|
|
27
|
DFO (Bagalkot)
|
EDS
|
User Agency (eeemwdbagalkot@gmail.com)
|
16/11/2021
|
Sir Please submit as per CCF letter Dtd 01-04-2021
|
|
28
|
User Agency (eeemwdbagalkot@gmail.com)
|
REPLY
|
DFO (Bagalkot)
|
23/12/2021
|
The correction have been made as per the instruction received
|
|
29
|
DFO (Bagalkot)
|
EDS
|
User Agency (eeemwdbagalkot@gmail.com)
|
27/12/2021
|
The file at Sl.No.9 in the documents uploaded under Additional Information in your proposal is not opening. Pls resubmit
|
|
30
|
User Agency (eeemwdbagalkot@gmail.com)
|
REPLY
|
DFO (Bagalkot)
|
27/12/2021
|
The correction have been made as per the instruction received
|
|
31
|
DFO (Bagalkot)
|
REPLY
|
CF (Belgaum)
|
30/12/2021
|
Sir Submit here report of FC violation
|
|
32
|
CF (Belgaum)
|
REPLY
|
Nodal Officer
|
02/03/2022
|
Compliance report submitted as per this office letter dated: 09-02-2022.
|
|
33
|
Nodal Officer
|
REPLY
|
State secretary
|
30/03/2022
|
the details here with submitted for further process
|
|
34
|
State secretary
|
REPLY
|
Regional Office
|
20/04/2022
|
eds
|
|
35
|
Regional Office
|
EDS
|
State secretary
|
05/05/2022
|
State Government has been requested vide letter dated 05-05-2022 to furnish action taken report on the construction of transmission line from existing 220 KV Mahalingapura line to 110 KV Substation at Jamakhandi during 1987 through forest area for a distance of 8.932 kms without approval under Forest Conservation Act, 1980.
|
|
36
|
State secretary
|
EDS
|
Nodal Officer
|
07/06/2022
|
eds
|
|
37
|
Nodal Officer
|
EDS
|
CF (Belgaum)
|
17/06/2022
|
please submit the information sought by Government of India
|
|
38
|
CF (Belgaum)
|
EDS
|
DFO (Bagalkot)
|
06/12/2022
|
please submit the information sought by Government of India
|
|
39
|
DFO (Bagalkot)
|
EDS
|
User Agency (eeemwdbagalkot@gmail.com)
|
13/12/2022
|
Pls Submit essential report as per GOI letter. enclosed GOI letter and FC guidelines
|
|
40
|
User Agency (eeemwdbagalkot@gmail.com)
|
REPLY
|
DFO (Bagalkot)
|
30/12/2022
|
The correction have been made as per the instruction received
|
|
41
|
DFO (Bagalkot)
|
REPLY
|
CF (Belgaum)
|
13/01/2023
|
submitting EDS reply reg.
|
|
42
|
CF (Belgaum)
|
REPLY
|
Nodal Officer
|
27/01/2023
|
Submitting EDS reply reg.
|
|
43
|
Nodal Officer
|
EDS
|
CF (Belgaum)
|
24/02/2023
|
please submit the required information in english version
|
|
44
|
CF (Belgaum)
|
EDS
|
DFO (Bagalkot)
|
06/03/2023
|
please submit the required information in english version
|
|
45
|
DFO (Bagalkot)
|
REPLY
|
CF (Belgaum)
|
18/07/2023
|
submitted
|
|
46
|
CF (Belgaum)
|
REPLY
|
Nodal Officer
|
18/07/2023
|
required information in english version Sir.
|
|
47
|
Nodal Officer
|
REPLY
|
State secretary
|
25/07/2023
|
the details sought by GOI is hereby renclosed for further process
|
|
48
|
State secretary
|
REPLY
|
Regional Office
|
03/08/2023
|
eds
|
|
49
|
Regional Office
|
EDS
|
State secretary
|
07/09/2023
|
Requested to furnish the ATR on violation taken up.
|
|
50
|
State secretary
|
EDS
|
Nodal Officer
|
30/09/2023
|
eds
|
|
51
|
Nodal Officer
|
EDS
|
CF (Belgaum)
|
06/10/2023
|
please obtain the information sought by GOI
|
|
52
|
CF (Belgaum)
|
EDS
|
DFO (Bagalkot)
|
07/10/2023
|
please obtain the information sought by GOI
|
|
53
|
DFO (Bagalkot)
|
EDS
|
User Agency (eeemwdbagalkot@gmail.com)
|
01/12/2023
|
Submit all essential sought details as per GOI direction
|
|
54
|
User Agency (eeemwdbagalkot@gmail.com)
|
REPLY
|
DFO (Bagalkot)
|
12/06/2024
|
The correction have been made as per the instruction received
|
|
55
|
DFO (Bagalkot)
|
REPLY
|
CF (Belgaum)
|
02/07/2024
|
I am submitting herewith enclosed report submitted by user agency
|
|
56
|
CF (Belgaum)
|
REPLY
|
Nodal Officer
|
07/08/2024
|
I am submitting herewith enclosed report submitted by user agency
|
|
57
|
Nodal Officer
|
REPLY
|
State secretary
|
29/03/2025
|
The reply is attached for information and further needfull action
|
|
58
|
State secretary
|
REPLY
|
Regional Office
|
25/04/2025
|
eds
|
|
59
|
Regional Office
|
EDS
|
State secretary
|
02/05/2025
|
State Government has been requested vide RO letter dated 02.05.2025 to submit recommendations of Project Steering Committee since it is a case violation and the proposal shall be processed by the Ministry.
|
|
60
|
State secretary
|
EDS
|
Nodal Officer
|
21/05/2025
|
eds
|
|
61
|
Nodal Officer
|
EDS
|
CF (Belgaum)
|
20/06/2025
|
submi the information sought by the GOI
|
|