Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Bellary)
|
EDS
|
User Agency (suresh.a@renewpower.in)
|
15/10/2022
|
it is directed to submit the complete proposal as per uploaded letter
|
|
2
|
User Agency (suresh.a@renewpower.in)
|
REPLY
|
DFO (Bellary)
|
31/12/2022
|
The correction have been made as per the instruction received
|
|
3
|
Nodal Officer
|
EDS
|
CF (Bellary)
|
15/02/2023
|
eds query
|
|
4
|
CF (Bellary)
|
EDS
|
DFO (Bellary)
|
15/02/2023
|
Submit the EDS as sought for by the Nodal Officer.
|
|
5
|
DFO (Bellary)
|
EDS
|
User Agency (suresh.a@renewpower.in)
|
22/02/2023
|
As directed by DCF, Vijayanagara, upload the revised maps in Form A of part-I for proposed area to be diverted.
|
|
6
|
User Agency (suresh.a@renewpower.in)
|
REPLY
|
DFO (Bellary)
|
24/02/2023
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Bellary)
|
REPLY
|
CF (Bellary)
|
24/02/2023
|
EDS submitted by DCF, Vijayanagara, the same has uploaded
|
|
8
|
CF (Bellary)
|
REPLY
|
Nodal Officer
|
08/03/2023
|
Compliance submitted to the 2 points as sought by your goodself.
|
|
9
|
State secretary
|
EDS
|
Nodal Officer
|
05/07/2023
|
eds
|
|
10
|
Nodal Officer
|
EDS
|
CF (Bellary)
|
13/07/2023
|
eds raised by gok
|
|
11
|
CF (Bellary)
|
EDS
|
DFO (Bellary)
|
21/07/2023
|
Submit information to the EDS
|
|
12
|
DFO (Bellary)
|
REPLY
|
CF (Bellary)
|
03/10/2023
|
EDS submitted by DCF, Vijaynagara. The same has been uploaded in parivesh portal
|
|
13
|
CF (Bellary)
|
REPLY
|
Nodal Officer
|
05/10/2023
|
Information Submitted
|
|
14
|
Nodal Officer
|
EDS
|
CF (Bellary)
|
08/11/2023
|
submit the eds reply
|
|
15
|
CF (Bellary)
|
REPLY
|
Nodal Officer
|
27/11/2023
|
English version report submitted
|
|
16
|
Nodal Officer
|
REPLY
|
State secretary
|
11/01/2024
|
EDS reply
|
|
17
|
State secretary
|
EDS
|
Nodal Officer
|
06/02/2024
|
eds
|
|
18
|
Nodal Officer
|
REPLY
|
State secretary
|
13/03/2024
|