Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
Nodal Officer
|
EDS
|
CF (Hassan)
|
27/10/2020
|
directed to transfer the online link to DCF Hassan for further verification the proposal
|
|
2
|
CF (Hassan)
|
EDS
|
DFO (Hassan)
|
04/11/2020
|
DCF, Hassan has been directed to submit compliance report to this office letter No/ A8 LAND FCA CR-13 2020-21, Date 16/10/2020
|
|
3
|
DFO (Hassan)
|
REPLY
|
CF (Hassan)
|
11/12/2020
|
Send other document
|
|
4
|
CF (Hassan)
|
EDS
|
DFO (Hassan)
|
14/12/2020
|
The file returned to DCF, Hassan with instruction to correction and re submit to this office.
|
|
5
|
DFO (Hassan)
|
EDS
|
User Agency (channegowdapwd@gmail.com)
|
16/12/2020
|
Send Other report
|
|
6
|
User Agency (channegowdapwd@gmail.com)
|
REPLY
|
DFO (Hassan)
|
29/12/2020
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Hassan)
|
REPLY
|
CF (Hassan)
|
16/01/2021
|
Re-diversion Proposal Corrected
|
|
8
|
CF (Hassan)
|
REPLY
|
Nodal Officer
|
17/02/2021
|
Proposal for improvement of existing road to Male Malleshwara Temple coming in 0.94 ha - Proposal submitted as per CCF, Hassan letter no:A8/LAND/FC/CR-13/2020-21, Dated: 17-02-2021.
|
|
9
|
Nodal Officer
|
EDS
|
CF (Hassan)
|
24/02/2021
|
you are directed to submit report with valid reasons for rejection or acceptance of the proposal
|
|
10
|
CF (Hassan)
|
REPLY
|
Nodal Officer
|
17/03/2021
|
As per the letter no:KFD/HOFF/A5-2(GFL)/16/2020-FC, Dated: 23-02-2021 of Nodal officer, Banglore the proposal submitted through online for needful action. (Recommendation letter enclosed)
|
|
11
|
Regional Office
|
EDS
|
State secretary
|
23/06/2021
|
FoC filed, alternate roads available etc.
|
|
12
|
State secretary
|
EDS
|
Nodal Officer
|
06/07/2021
|
eds
|
|
13
|
Nodal Officer
|
EDS
|
CF (Hassan)
|
09/07/2021
|
please submit he information sought by GOI
|
|
14
|
CF (Hassan)
|
EDS
|
DFO (Hassan)
|
13/07/2021
|
Sent to DCF, Hassan as per the Nodal Officer, Bangalore letter dated 09-07-2021
|
|
15
|
DFO (Hassan)
|
REPLY
|
CF (Hassan)
|
31/07/2021
|
Rationed Clarification & information details uploaded
|
|
16
|
CF (Hassan)
|
REPLY
|
Nodal Officer
|
02/08/2021
|
Compliance report submitted as per the directions of PCCF, FC & Nodal Officer (FCA), Bengaluru vide letter dated: 09-07-2021.
|
|
17
|
Nodal Officer
|
REPLY
|
State secretary
|
01/09/2021
|
the details are enclosed for further necessary action
|
|
18
|
State secretary
|
REPLY
|
Regional Office
|
18/09/2021
|
EDs
|
|