Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
CF (Gulbarga)
|
EDS
|
DFO (Bidar)
|
25/06/2019
|
submit proposal As per Circular No. A5/5/pr/fca/36./2018 dated 14.11.2018
|
|
2
|
DFO (Bidar)
|
REPLY
|
CF (Gulbarga)
|
25/06/2019
|
Updated
|
|
3
|
Nodal Officer
|
EDS
|
CF (Gulbarga)
|
16/09/2019
|
Identify the correct CA land & upload the correct documents
|
|
4
|
CF (Gulbarga)
|
EDS
|
DFO (Bidar)
|
21/10/2019
|
as per apccf fc bangalore letter dated 05.09.2019
|
|
5
|
DFO (Bidar)
|
EDS
|
User Agency (chavanee0@gmail.com)
|
22/10/2019
|
Alternate CA Land to be proposed as per the directions of APCCF FC letter dated 05.09.2019 and CA land is identified vide DCF letter dated 21/10/2019. Update details in part 1 along with concurrence from deputy commissioner and submit for further processing
|
|
6
|
User Agency (chavanee0@gmail.com)
|
REPLY
|
DFO (Bidar)
|
26/11/2019
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Bidar)
|
REPLY
|
CF (Gulbarga)
|
19/12/2019
|
As per attachment
|
|
8
|
CF (Gulbarga)
|
REPLY
|
Nodal Officer
|
26/12/2019
|
Recommended
|
|
9
|
Regional Office
|
EDS
|
State secretary
|
05/06/2020
|
Revised proposal
|
|
10
|
State secretary
|
EDS
|
Nodal Officer
|
26/06/2020
|
EDS
|
|
11
|
Nodal Officer
|
EDS
|
CF (Gulbarga)
|
26/06/2020
|
communication of EDS of GOI
|
|
12
|
CF (Gulbarga)
|
EDS
|
DFO (Bidar)
|
26/06/2020
|
as per pccf letter
|
|
13
|
DFO (Bidar)
|
EDS
|
User Agency (chavanee0@gmail.com)
|
26/06/2020
|
as per pccf letter
|
|
14
|
User Agency (chavanee0@gmail.com)
|
REPLY
|
DFO (Bidar)
|
03/07/2020
|
The correction have been made as per the instruction received
|
|
15
|
DFO (Bidar)
|
EDS
|
User Agency (chavanee0@gmail.com)
|
16/07/2020
|
As per Attachment
|
|
16
|
User Agency (chavanee0@gmail.com)
|
REPLY
|
DFO (Bidar)
|
22/07/2020
|
The correction have been made as per the instruction received
|
|
17
|
DFO (Bidar)
|
REPLY
|
CF (Gulbarga)
|
03/08/2020
|
As per attachment
|
|
18
|
CF (Gulbarga)
|
REPLY
|
Nodal Officer
|
10/08/2020
|
Recommended
|
|
19
|
Nodal Officer
|
REPLY
|
State secretary
|
07/10/2020
|
revised proposal for extent 20.0724 ha from 40.79 ha
|
|
20
|
State secretary
|
REPLY
|
Regional Office
|
05/11/2020
|
EDS
|
|