TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/KA/ROAD/21837/2016              (ii). Name of Project for which Forest Land is required : Approach road for Bellary Iron Ore Mine over an extent of 4.74 Ha.              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : JSW Steel Ltd. has been declared the successful bidder in vide letter no. DMG/MLS/CCA/12/2365/2016-17 by Dept. of Mines & Geology. In order to commence the mining operations, we are in need of an approach road to the mines. There is an existing road which was used earlier for movement. We are putti              (iv). File no. : 8-112/2000-FC Vol              (v). State : Karnataka              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 4.74
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentMoEFCC,New DelhiStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/KA/ROAD/21837/201617/10/201617/12/2016  28/10/2016   19/12/2016  29/11/2016   29/12/2016   06/01/2017 Bellary :18/01/2017Bellary:
  20/05/2017 (Bellary)

Karnataka:
03/06/2017
Karnataka:
15/07/2017
28/08/201719/12/2017
By :Head Office
Karnataka
14/06/2022
25/09/2023
By :Head Office
  
C. Essential Details Sought History
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
  Query raised by DFO (Bellary) on:31/01/2017  
Replied by UA on :20/03/2017  
Query raised by DFO (Bellary) on:19/05/2017  
Replied by UA on :19/05/2017  
D. Essential Details Sought History (Stage-II)
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by MoEFCC,New Delhi 06/07/2022  
Replied by State Government (Karnataka) on:25/04/2023  
Query raised by MoEFCC,New Delhi 13/07/2023  
Replied by State Government (Karnataka) on:14/09/2023  
Query raised by State Government (Karnataka) on:25/10/2022  
Replied by Nodal Officer (Karnataka) on:03/04/2023  
Query raised by State Government (Karnataka) on:14/07/2023  
Replied by Nodal Officer (Karnataka) on:22/08/2023  
Query raised by Nodal Officer on:25/10/2022  
Replied by UA on :17/03/2023  
Query raised by Nodal Officer on:21/07/2023  
Replied by UA on :27/07/2023  
Query raised by Nodal Officer on:02/08/2023  
Replied by UA on :03/08/2023  
NOTE:- Stage-II Approval accorded by : Head Office .