TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/KA/ROAD/10844/2015              (ii). Name of Project for which Forest Land is required : Raghavendra Stone crushing Works, Tattisar              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Shifting the exciting stone crushing unit to Malki Sy.No.35 of Tattisar village,Sirsi Taluk, Uttara kannada District, Hence the approach road to above said site is passing through Forest Sy.No. 146 of Tattisar village Hulekal Range of Sirsi Division,Uttara kannada District              (iv). File no. : 4-KRB 1104/2017-BAN              (v). State : Karnataka              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.081
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/KA/ROAD/10844/201529/03/201527/05/2015  17/04/2015   28/05/2015  16/05/2015   10/06/2015   19/06/2015 Sirsi :23/06/2015Kanara:
  22/07/2015 (Sirsi)

Karnataka:
30/12/2015
Karnataka:
02/01/2016
Bangalore:
02/02/2017
06/10/2017
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Bangalore) on:07/02/2017  
Replied by State Government(Karnataka) on:04/10/2017  
Query raised by State Government (Karnataka) on:22/05/2017  
Replied by Nodal Officer (Karnataka) on:25/09/2017  
Query raised by State Government (Karnataka) on:27/09/2017  
Replied by Nodal Officer (Karnataka) on:27/09/2017  
Query raised by Circle (Kanara) on:26/11/2015  
Replied by DFO (Sirsi) on:15/12/2015  
Query raised by DFO (Sirsi) on:05/12/2015  
Replied by UA on :09/12/2015  
NOTE:- Stage-I Approval accorded by : Regional Office .