TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/KA/QRY/46423/2020              (ii). Name of Project for which Forest Land is required : Building Stone Quarry in Forest SY No 215/A/1A of Arav Village, Karwar Taluka, Uttar Kannada District.              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of 0.4928 ha of minor forest land in Forest SY No. 215/A/1A of Arav in Karwar taluka, Uttar Kannada District for building stone quarry and M-sand.              (iv). State : Karnataka              (v). Category of the Project : Quarrying              (vi). Shape of forest land proposed to be diverted : Non Linear              (vii). Area of forest land proposed for diversion(in ha.): 0.4928
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/KA/QRY/46423/202016/06/202029/06/2020   04/07/2020   27/07/2020   03/08/2020 Karwar :07/08/2020Kanara:
  19/05/2021 (Karwar)

Karnataka:
19/07/2021
Karnataka:
16/08/2021
Bangalore:
07/11/2022
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Bangalore) on:06/12/2022  
Query raised by State Government (Karnataka) on:02/01/2023  
Replied by Nodal Officer (Karnataka) on:13/05/2025  
Query raised by Nodal Officer (Karnataka) on:24/01/2023  
Replied by Circle(Kanara) on:01/03/2024  
Query raised by Nodal Officer (Karnataka) on:01/08/2024  
Replied by Circle(Kanara) on:18/01/2025  
Query raised by Nodal Officer (Karnataka) on:20/03/2025  
Replied by Circle(Kanara) on:13/05/2025  
Query raised by Circle (Kanara) on:06/02/2023  
Replied by DFO (Karwar) on:03/07/2023  
Query raised by Circle (Kanara) on:23/08/2023  
Replied by DFO (Karwar) on:16/02/2024  
Query raised by Circle (Kanara) on:06/08/2024  
Replied by DFO (Karwar) on:04/01/2025  
Query raised by Circle (Kanara) on:27/03/2025  
Replied by DFO (Karwar) on:12/05/2025  
Query raised by DFO (Karwar) on:16/12/2020  
Replied by UA on :18/03/2021  
Query raised by DFO (Karwar) on:17/02/2023  
Replied by UA on :02/07/2023  
Query raised by DFO (Karwar) on:23/08/2023  
Replied by UA on :03/10/2023  
Query raised by DFO (Karwar) on:21/10/2023  
Replied by UA on :22/10/2023  
Query raised by DFO (Karwar) on:26/12/2024  
Replied by UA on :29/12/2024  
NOTE:- Proposal is pending at State Government due to EDS raised by Regional Office .