| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
Regional Office
|
EDS
|
State secretary
|
03/05/2022
|
State Government has been requested vide letter dated 03-05-2022 to furnish information, clarifications on justification for opening new quarry, uploading of proper CA scheme in the web portal, clear map depicting various components of quarry for proposed diversion, legal status of the land required for crushing unit, clarification on plants planted per ha., quarry plan approved from the Competent authority and status of environmental clearance etc.
|
|
|
2
|
State secretary
|
EDS
|
Nodal Officer
|
31/05/2022
|
eds
|
|
|
3
|
Nodal Officer
|
EDS
|
CF (Kanara)
|
02/06/2022
|
communication of EDS query
|
|
|
4
|
CF (Kanara)
|
EDS
|
DFO (Karwar)
|
04/06/2022
|
EDS
|
|
|
5
|
DFO (Karwar)
|
REPLY
|
CF (Kanara)
|
04/06/2022
|
Quarry Reply
|
|
|
6
|
CF (Kanara)
|
REPLY
|
Nodal Officer
|
10/06/2022
|
EDS
|
|
|
7
|
Nodal Officer
|
EDS
|
CF (Kanara)
|
10/08/2022
|
please obtain letter of intent from UA competent authority
|
|
|
8
|
CF (Kanara)
|
EDS
|
DFO (Karwar)
|
22/08/2022
|
eds
|
|
|
9
|
DFO (Karwar)
|
REPLY
|
CF (Kanara)
|
02/09/2022
|
Reply of EDS raised by PCCF (FC) & Nodal Officer (FCA) Bangalore.
|
|
|
10
|
CF (Kanara)
|
EDS
|
DFO (Karwar)
|
05/09/2022
|
Incomplete information
|
|
|
11
|
DFO (Karwar)
|
REPLY
|
CF (Kanara)
|
05/09/2022
|
Reply to query raised by PCCF (FC) & Nodal Officer (FCA) Bengaluru
|
|
|
12
|
CF (Kanara)
|
REPLY
|
Nodal Officer
|
05/09/2022
|
eds re submit
|
|
|
13
|
Nodal Officer
|
EDS
|
CF (Kanara)
|
17/12/2022
|
please submi the information obatin from the UA
|
|
|
14
|
CF (Kanara)
|
EDS
|
DFO (Karwar)
|
19/12/2022
|
EDS
|
|
|
15
|
DFO (Karwar)
|
EDS
|
User Agency (shivaprasadpillai@gmail.com)
|
19/12/2022
|
Query raised by PCCF FC Benagaluru
|
|
|
16
|
User Agency (shivaprasadpillai@gmail.com)
|
REPLY
|
DFO (Karwar)
|
04/02/2023
|
The correction have been made as per the instruction received
|
|
|
17
|
DFO (Karwar)
|
REPLY
|
CF (Kanara)
|
04/02/2023
|
EDS reply for quarry plan.
|
|
|
18
|
CF (Kanara)
|
EDS
|
DFO (Karwar)
|
19/03/2023
|
EDS
|
|
|
19
|
DFO (Karwar)
|
REPLY
|
CF (Kanara)
|
20/03/2023
|
EDS reply- CF ltr.
|
|
|
20
|
CF (Kanara)
|
EDS
|
DFO (Karwar)
|
12/01/2024
|
eds
|
|
|
21
|
DFO (Karwar)
|
EDS
|
User Agency (shivaprasadpillai@gmail.com)
|
16/02/2024
|
Query from Direcot, Mines and Geology Dept. Bengaluru
|
|
|
22
|
User Agency (shivaprasadpillai@gmail.com)
|
REPLY
|
DFO (Karwar)
|
06/07/2024
|
The correction have been made as per the instruction received
|
|
|
23
|
DFO (Karwar)
|
EDS
|
User Agency (shivaprasadpillai@gmail.com)
|
24/09/2024
|
Submit Maps of surrounding area
|
|
|
24
|
User Agency (shivaprasadpillai@gmail.com)
|
REPLY
|
DFO (Karwar)
|
13/11/2024
|
The correction have been made as per the instruction received
|
|
|
25
|
DFO (Karwar)
|
REPLY
|
CF (Kanara)
|
10/02/2025
|
EDS Reply
|
|
|
26
|
CF (Kanara)
|
REPLY
|
Nodal Officer
|
10/02/2025
|
EDS Reply
|
|
|
27
|
Nodal Officer
|
REPLY
|
State secretary
|
21/03/2025
|
The reply is submitted for further needful
|
|
|
28
|
State secretary
|
EDS
|
Nodal Officer
|
24/03/2025
|
eds
|
|
|
29
|
Nodal Officer
|
REPLY
|
State secretary
|
24/03/2025
|
The revised reply copy is hereby enclosed for further needfull
|
|
|
30
|
State secretary
|
EDS
|
Nodal Officer
|
06/05/2025
|
eds
|
|
|
31
|
Nodal Officer
|
REPLY
|
State secretary
|
09/05/2025
|
This office had conducted the PSC meeting on 07-05-2025 and decided to accept the proposal for recommendation. the copy of the PSC proceedings is attached for further needfull
|
|
|
32
|
State secretary
|
REPLY
|
Regional Office
|
14/05/2025
|
EDS
|
|
|
33
|
Head Office
|
EDS
|
State secretary
|
30/06/2025
|
EDS
|
|
|
34
|
State secretary
|
EDS
|
Nodal Officer
|
14/07/2025
|
eds
|
|
|
35
|
Nodal Officer
|
EDS
|
CF (Kanara)
|
04/08/2025
|
Submit the report sought by the GOI
|
|
|
36
|
CF (Kanara)
|
EDS
|
DFO (Karwar)
|
05/08/2025
|
EDS
|
|
|
37
|
DFO (Karwar)
|
EDS
|
User Agency (shivaprasadpillai@gmail.com)
|
14/08/2025
|
EDS raised by GOI
|
|
|
38
|
User Agency (shivaprasadpillai@gmail.com)
|
REPLY
|
DFO (Karwar)
|
13/09/2025
|
The correction have been made as per the instruction received
|
|