Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Gadag)
|
EDS
|
User Agency (aeemisd.gadag@gmail.com)
|
22/08/2022
|
It has been seen that during inspection conducted on 17.08.2022 by the DCF, Gadag Division along with field staff, the pipeline work has already been done in the Singatarayankere forest of Mundargi Range. That portion of the forest needs to be updated in the application in consultation with the field staff of Mundargi Range. Hence the proposal is returned for necessary changes and onward submission
|
|
2
|
User Agency (aeemisd.gadag@gmail.com)
|
REPLY
|
DFO (Gadag)
|
24/08/2022
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Gadag)
|
EDS
|
User Agency (aeemisd.gadag@gmail.com)
|
24/08/2022
|
The proposal is returned for necessary changes in Part-1 of A1 , ii, vi
|
|
4
|
User Agency (aeemisd.gadag@gmail.com)
|
REPLY
|
DFO (Gadag)
|
26/08/2022
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Gadag)
|
EDS
|
User Agency (aeemisd.gadag@gmail.com)
|
30/08/2022
|
The proposal is returned for necessary changes in Topo map and Geo referenced map
|
|
6
|
User Agency (aeemisd.gadag@gmail.com)
|
REPLY
|
DFO (Gadag)
|
09/09/2022
|
The correction have been made as per the instruction received
|
|