Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Bagalkot)
|
EDS
|
User Agency (metaguddaraju03@gmail.com)
|
11/10/2021
|
Observed online proposal and hard copies 1. Extent 0.0138ha mention in hard copies but in online 0.0318 ha 2. In hard copies not sumit No alternative land certificate from District commissioner. hence submit Correct maps and essential documents.
|
|
2
|
User Agency (metaguddaraju03@gmail.com)
|
REPLY
|
DFO (Bagalkot)
|
30/10/2021
|
The correction have been made as per the instruction received
|
|
3
|
CF (Belgaum)
|
EDS
|
DFO (Bagalkot)
|
07/01/2022
|
Hard copy not submit this office till today hence proposal link returned
|
|
4
|
DFO (Bagalkot)
|
EDS
|
User Agency (metaguddaraju03@gmail.com)
|
27/01/2022
|
You are not submit the DC letter for Non-Forest land not available certificate for laying of proposed pipeline.
|
|
5
|
User Agency (metaguddaraju03@gmail.com)
|
REPLY
|
DFO (Bagalkot)
|
09/02/2022
|
The correction have been made as per the instruction received
|
|
6
|
DFO (Bagalkot)
|
REPLY
|
CF (Belgaum)
|
15/06/2022
|
Hard Copies submitted from this office vide this office letter No. B2/GFL/Proposal/0.0138/CR/2021-22 Dtd: 13-04-2022
|
|