| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
DFO (Dharwad)
|
EDS
|
User Agency (prakash_kpl@outlook.com)
|
22/07/2022
|
Area was jointly inspected by Forest Officials including DCF, ACF and RFO with User agency. At several points, artificial stones were coming inside fenced area of Nruptungabetta. Hence User agency is instructed to conduct another survey in presence of forest department team.
|
|
|
2
|
User Agency (prakash_kpl@outlook.com)
|
REPLY
|
DFO (Dharwad)
|
07/10/2023
|
The correction have been made as per the instruction received
|
|
|
3
|
State secretary
|
EDS
|
Nodal Officer
|
11/06/2024
|
eds
|
|
|
4
|
Nodal Officer
|
REPLY
|
State secretary
|
20/07/2024
|
EDS Reply
|
|
|
5
|
Regional Office
|
EDS
|
State secretary
|
30/05/2025
|
State Government was requested on 30.05.2025 to submit specific comments on violation, suitability certificate of CA etc.
|
|
|
6
|
State secretary
|
EDS
|
Nodal Officer
|
02/07/2025
|
eds
|
|
|
7
|
Nodal Officer
|
EDS
|
CF (Dharwad)
|
09/07/2025
|
Submit EDS reply
|
|
|
8
|
CF (Dharwad)
|
REPLY
|
Nodal Officer
|
29/12/2025
|
The DCF, Dharwad report is attached here with this letter and forwarded to your kind perusal.
|
|
|
9
|
Nodal Officer
|
REPLY
|
State secretary
|
30/12/2025
|
EDS reply submitted.
|
|
|
10
|
State secretary
|
REPLY
|
Regional Office
|
13/01/2026
|
EDS
|
|
|
11
|
Regional Office
|
EDS
|
State secretary
|
11/02/2026
|
State Govt. has been requested vide letter dated 11.02.2026 to submit the proposal to MoEFCC, New Delhi, since the Forest land is under continuous possession of user agency even after the expiry of the lease period in violation of VSESA, 1980.
|
|
|
12
|
State secretary
|
EDS
|
Nodal Officer
|
23/02/2026
|
eds
|
|
|
13
|
Nodal Officer
|
EDS
|
CF (Dharwad)
|
07/04/2026
|
Once again GoI has sought the action taken report and details of erring officials as per Rule of Van Sanrakshan Evam Samvardhan Rules 2023. You are hereby directed to submit the report.
|
|