TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/KA/Others/25293/2017              (ii). Name of Project for which Forest Land is required : For re-construction existing old Temple & approach Road at Tenka Kajekar Village & Block, Bantwala Range, Mangalore Division, D.K District in favour President, Shri Krishna Temple, Karla. Tenkakajekar (V), Bantwala (T), D.K. District.              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of 0.9713 ha of forest land in Sy.No.61/11P1 of Tenka Kajekar Village, Tenka Kajekar Block, Bantwala Range, Mangalore Division, for re-construction existing old Temple & approach road at Non-Forest Land in favour of the President, Shri Krishna Temple, Karla, Mangalore              (iv). State : Karnataka              (v). Category of the Project : Others              (vi). Shape of forest land proposed to be diverted : Non Linear              (vii). Area of forest land proposed for diversion(in ha.): 0.9713
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/KA/Others/25293/201725/03/201718/09/2019  12/02/2018  28/06/2017  31/03/2017   21/08/2020  26/08/2019  02/02/2018  17/06/2017   05/09/2020   18/09/2020 Mangalore :05/10/2020Mangalore:
  20/01/2021 (Mangalore)

Karnataka:
01/02/2021
Karnataka:
24/02/2021
Bangalore:
15/12/2021
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Bangalore) on:28/01/2022  
Query raised by State Government (Karnataka) on:29/03/2021  
Replied by Nodal Officer (Karnataka) on:15/07/2021  
Query raised by State Government (Karnataka) on:28/07/2021  
Replied by Nodal Officer (Karnataka) on:29/07/2021  
Query raised by State Government (Karnataka) on:24/02/2022  
Replied by Nodal Officer (Karnataka) on:17/07/2026  
Query raised by Nodal Officer (Karnataka) on:03/04/2021  
Replied by Circle(Mangalore) on:29/06/2021  
Query raised by Nodal Officer (Karnataka) on:25/02/2022  
Replied by Circle(Mangalore) on:06/07/2026  
Query raised by Circle (Mangalore) on:05/04/2021  
Replied by DFO (Mangalore) on:15/06/2021  
Query raised by Circle (Mangalore) on:28/02/2022  
Replied by DFO (Mangalore) on:06/07/2026  
Query raised by DFO (Mangalore) on:08/12/2020  
Replied by UA on :29/12/2020  
Query raised by DFO (Mangalore) on:05/04/2021  
Replied by UA on :08/06/2021  
Query raised by DFO (Mangalore) on:06/03/2022  
Replied by UA on :06/07/2026  
NOTE:- Proposal is pending at State Government due to EDS raised by Regional Office .