Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
CF (Mangalore)
|
EDS
|
DFO (Mangalore)
|
16/02/2017
|
In the site inspection report it is mentioned that the proposed site is nor RF- Clarify.In Sl. No. 13 of Part II CA details donot match with the Area proposed for Diversion- Clarify
|
|
2
|
DFO (Mangalore)
|
REPLY
|
CF (Mangalore)
|
18/02/2017
|
It is to clarify that, the proposed forest area for diversion is a forest area and the error was due to typographical mistake. Further, the area required is less than 1ha, and CA is not required in this case but in online filing system, some details are to be furnished to continue. Hence, a dummy CA details are uploaded.
|
|
3
|
Regional Office
|
EDS
|
State secretary
|
08/08/2017
|
RoFR certificate etc.
|
|
4
|
State secretary
|
EDS
|
Nodal Officer
|
27/09/2017
|
To submit EDS as per MoEF letters dated 08.08.2017 and 08.09.2017
|
|
5
|
Nodal Officer
|
EDS
|
CF (Mangalore)
|
06/10/2017
|
Compliance to the letter dated 08-09-2017 shall be submitted as enclosed.
|
|
6
|
CF (Mangalore)
|
EDS
|
DFO (Mangalore)
|
23/10/2017
|
provide the clarifications sought in the letter
|
|
7
|
DFO (Mangalore)
|
REPLY
|
CF (Mangalore)
|
26/10/2017
|
FRA Certificate and report enclosed.
|
|
8
|
CF (Mangalore)
|
EDS
|
DFO (Mangalore)
|
13/11/2017
|
Compliance to the letter dated 08-09-2017 shall be submitted as enclosed by Nodal officer
|
|
9
|
DFO (Mangalore)
|
REPLY
|
CF (Mangalore)
|
15/12/2017
|
Compliance report submitted.
|
|
10
|
CF (Mangalore)
|
REPLY
|
Nodal Officer
|
21/12/2017
|
Letter of DCF containing clarifications for the points raised is here with enclosed for needful action
|
|
11
|
Nodal Officer
|
REPLY
|
State secretary
|
23/12/2017
|
Report submitted on 30-11-2017.
|
|
12
|
State secretary
|
REPLY
|
Regional Office
|
25/01/2018
|
Requisite information has been sent vide this office letter No.FEE 54 FLL 2017 dated 12.01.2018
|
|