TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/KA/OFC/143839/2021              (ii). Name of Project for which Forest Land is required : Jio laying Optical Fiber Cable along the RoW of the road from Chincholi-Chimmanchodi & Kalluru-Lingapura in Chincholi Taluk of Kalburgi and Chitaguppa Talukf of Bidar District , Kalburgi Forest Divisions and Bidar Forest Division              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Jio laying Optical Fiber Cable along RoW of the road from in Chincholi-Chimannchodi and Kaluuru-Lingapura Stretch in Gulbarga District for better telecommunication network for various sector.              (iv). File no. : F.No.4-KRB1446/2023-BAN              (v). State : Karnataka              (vi). Category of the Project : Optical Fibre Cable              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.855293
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/KA/OFC/143839/202121/06/202127/05/2022  19/07/2021   10/06/2022  16/05/2022   30/06/2022   18/07/2022

Gulbarga :18/07/2022


Bidar :18/07/2022

Gulbarga:
  01/09/2022 (Gulbarga)

Gulbarga:
  02/09/2022 (Bidar)

Karnataka:
07/09/2022
Karnataka:
03/11/2022
Bangalore:
23/03/2023
18/11/2024
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Bangalore) on:10/04/2023  
Replied by State Government(Karnataka) on:19/10/2024  
Query raised by State Government (Karnataka) on:10/01/2023  
Replied by Nodal Officer (Karnataka) on:24/01/2023  
Query raised by State Government (Karnataka) on:25/04/2023  
Replied by Nodal Officer (Karnataka) on:17/01/2024  
Query raised by Nodal Officer (Karnataka) on:08/05/2023  
Replied by Circle(Gulbarga) on:14/12/2023  
Query raised by Circle (Gulbarga) on:11/05/2023  
Replied by DFO (Gulbarga) on:06/06/2023  
Query raised by Circle (Gulbarga) on:11/05/2023  
Replied by DFO (Bidar) on:27/11/2023  
Query raised by DFO (Gulbarga) on:25/07/2022  
Replied by UA on :02/08/2022  
Query raised by DFO (Bidar) on:26/08/2022  
Replied by UA on :27/08/2022  
Query raised by DFO (Bidar) on:12/06/2023  
Replied by UA on :21/06/2023  
Query raised by DFO (Bidar) on:10/07/2023  
Replied by UA on :14/07/2023  
Query raised by DFO (Bidar) on:19/07/2023  
Replied by UA on :07/08/2023  
Query raised by DFO (Bidar) on:17/08/2023  
Replied by UA on :02/09/2023  
Query raised by DFO (Bidar) on:16/10/2023  
Replied by UA on :25/10/2023  
Query raised by DFO (Bidar) on:15/11/2023  
Replied by UA on :20/11/2023  
NOTE:- Stage-I Approval accorded by : Regional Office .