Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Gulbarga)
|
EDS
|
User Agency (babu.veerabhadre@ril.com)
|
25/07/2022
|
1. Lachmasagar CH no. 30988.892 m to Chikkalingadalli CH No. 8700.00m it is falls under “CHINCHOLI WIDLIFE SANCTUARY”, hence wildlife proposal to be submit by online to grant the permission from the National Board of Wildlife.
2. The OFC line passing through the Chindanoor village survey No. 47 is forest land, the length the OFC line is left out.
3. The OFC line passing through the Shadipur village survey No. 124 is forest land, the length of the OFC line is left out. The Shadipur Village Carastral Map not enclosed.
4. Tumkunta survey no. 26 is forest land in Topo Sheet survey number not shown in forest survey number in index.
Hence, your requested to attened the observation and re-submit the proposal.
|
|
2
|
User Agency (babu.veerabhadre@ril.com)
|
REPLY
|
DFO (Gulbarga)
|
02/08/2022
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Bidar)
|
EDS
|
User Agency (babu.veerabhadre@ril.com)
|
26/08/2022
|
As per attachment.
|
|
4
|
User Agency (babu.veerabhadre@ril.com)
|
REPLY
|
DFO (Bidar)
|
27/08/2022
|
The correction have been made as per the instruction received
|
|
5
|
State secretary
|
EDS
|
Nodal Officer
|
10/01/2023
|
eds
|
|
6
|
Nodal Officer
|
REPLY
|
State secretary
|
24/01/2023
|
Reply submitted
|
|
7
|
Regional Office
|
EDS
|
State secretary
|
10/04/2023
|
State Government has been requested vide letter dated 06-04-2023 to effect the changes in the Part-I, Part-II & to upload the revised KML files since the area is revised from 0.227598 to 0.310339 in Bidar Forest Division and to submit the recommendation of Standing Committee of National Board for Wildlife since the proposed area contains trees felling in the Chincholi Wildlife Sanctuary.
|
|
8
|
State secretary
|
EDS
|
Nodal Officer
|
25/04/2023
|
eds
|
|
9
|
Nodal Officer
|
EDS
|
CF (Gulbarga)
|
08/05/2023
|
You are hereby directed to submit the GoK required information
|
|
10
|
CF (Gulbarga)
|
EDS
|
DFO (Bidar)
|
11/05/2023
|
as per nodal officer and GOI
|
|
11
|
CF (Gulbarga)
|
EDS
|
DFO (Gulbarga)
|
11/05/2023
|
as per nodal officer and GOI
|
|
12
|
DFO (Gulbarga)
|
REPLY
|
CF (Gulbarga)
|
06/06/2023
|
Clarification letter uploaded
|
|
13
|
DFO (Bidar)
|
EDS
|
User Agency (babu.veerabhadre@ril.com)
|
12/06/2023
|
You are here by requested to attend the EDS raised by GOI
|
|
14
|
User Agency (babu.veerabhadre@ril.com)
|
REPLY
|
DFO (Bidar)
|
21/06/2023
|
The correction have been made as per the instruction received
|
|
15
|
DFO (Bidar)
|
EDS
|
User Agency (babu.veerabhadre@ril.com)
|
10/07/2023
|
As per attachment.
|
|
16
|
User Agency (babu.veerabhadre@ril.com)
|
REPLY
|
DFO (Bidar)
|
14/07/2023
|
The correction have been made as per the instruction received
|
|
17
|
DFO (Bidar)
|
EDS
|
User Agency (babu.veerabhadre@ril.com)
|
19/07/2023
|
As per attachment
|
|
18
|
User Agency (babu.veerabhadre@ril.com)
|
REPLY
|
DFO (Bidar)
|
07/08/2023
|
The correction have been made as per the instruction received
|
|
19
|
DFO (Bidar)
|
EDS
|
User Agency (babu.veerabhadre@ril.com)
|
17/08/2023
|
Maps submitted to this office vide your letter dated 07.08.2023. The survey number wise area break-up is not mentioned. Instead, overall extent is given village wise. Hence, it is requested to provide the necessary details for further processing of the proposal.
|
|
20
|
User Agency (babu.veerabhadre@ril.com)
|
REPLY
|
DFO (Bidar)
|
02/09/2023
|
The correction have been made as per the instruction received
|
|
21
|
DFO (Bidar)
|
EDS
|
User Agency (babu.veerabhadre@ril.com)
|
16/10/2023
|
Requested to enter the villagewise and survey numberwise area extent.
|
|
22
|
User Agency (babu.veerabhadre@ril.com)
|
REPLY
|
DFO (Bidar)
|
25/10/2023
|
The correction have been made as per the instruction received
|
|
23
|
DFO (Bidar)
|
EDS
|
User Agency (babu.veerabhadre@ril.com)
|
15/11/2023
|
Requesting you to update villagewise area component in part-I
|
|
24
|
User Agency (babu.veerabhadre@ril.com)
|
REPLY
|
DFO (Bidar)
|
20/11/2023
|
The correction have been made as per the instruction received
|
|
25
|
DFO (Bidar)
|
REPLY
|
CF (Gulbarga)
|
27/11/2023
|
As per attachment
|
|
26
|
CF (Gulbarga)
|
REPLY
|
Nodal Officer
|
14/12/2023
|
Recommended as per DCF report
|
|
27
|
Nodal Officer
|
REPLY
|
State secretary
|
17/01/2024
|
eds reply
|
|
28
|
State secretary
|
REPLY
|
Regional Office
|
19/10/2024
|
eds
|
|