Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Shimoga)
|
EDS
|
User Agency (babu.veerabhadre@ril.com)
|
15/12/2022
|
As per field inspection report certain queries are raised and necessary information is required to further process the proposal
|
|
2
|
User Agency (babu.veerabhadre@ril.com)
|
REPLY
|
DFO (Shimoga)
|
05/06/2024
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Shimoga)
|
EDS
|
User Agency (babu.veerabhadre@ril.com)
|
27/01/2025
|
Please provide KML file of the proposed land
|
|
4
|
User Agency (babu.veerabhadre@ril.com)
|
REPLY
|
DFO (Shimoga)
|
17/02/2025
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Shimoga)
|
EDS
|
User Agency (babu.veerabhadre@ril.com)
|
22/04/2025
|
1. Individual village survey number wise extent to be provided and survey numbers not to be clubbed.
2. KML file submitted goes outside the ROW of the existing road. The kml needs to be corrected and uploaded.
3. Few individual marked village maps are not submitted. That needs to be submitted.
4. Few villages in which the optical fibre passes is not included in the proposal for diversion and few private lands are included as forest areas. That needs to be corrected and uploaded.
5. The area proposed for diversion comes in and within the eco-sensitive zone of shettihalli and someshwara wildlife sanctuary. This needs to be clarified and updated in Part 1 of the proposal.
|
|