| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
DFO (Bellary)
|
EDS
|
User Agency (sdkhatavkar@gmail.com)
|
31/01/2015
|
The proposal submitted is incomplete. Please submit proposal as per this office letter dated 26.12.2014.
|
|
|
2
|
User Agency (sdkhatavkar@gmail.com)
|
REPLY
|
DFO (Bellary)
|
10/03/2015
|
As desired by DCF, Bellary vide his letter no.M1/MNG/NMDC/ML NO.1111/2013-14/1942 dt.30.12.2014. We are submitting pointwise reply for necessary action on our proposal. Further complete proposal in 10 sets will be submitted to DCF.
|
|
|
3
|
DFO (Bellary)
|
EDS
|
User Agency (sdkhatavkar@gmail.com)
|
14/05/2015
|
some of the documents such as Safety Zone Map, CEC sketch, cost benifit analysis, Mining plan
|
|
|
4
|
User Agency (sdkhatavkar@gmail.com)
|
REPLY
|
DFO (Bellary)
|
25/05/2015
|
As desired by DCF, Bellary vide his letter no.M1/MNG/NMDC/ML NO.1111/2013-14/189 dt.05.05.2015. We are here with submitting pointwise reply for necessary action on our proposal.
|
|
|
5
|
DFO (Bellary)
|
EDS
|
User Agency (sdkhatavkar@gmail.com)
|
03/04/2016
|
To identify non-forest land over an extent of 167.63 ha.
|
|
|
6
|
User Agency (sdkhatavkar@gmail.com)
|
REPLY
|
DFO (Bellary)
|
09/06/2016
|
The correction have been made as per the instruction received
|
|
|
7
|
DFO (Bellary)
|
EDS
|
User Agency (sdkhatavkar@gmail.com)
|
23/07/2016
|
Not incorporated necessary document to proposal
|
|
|
8
|
User Agency (sdkhatavkar@gmail.com)
|
REPLY
|
DFO (Bellary)
|
11/08/2016
|
The correction have been made as per the instruction received
|
|
|
9
|
DFO (Bellary)
|
EDS
|
User Agency (sdkhatavkar@gmail.com)
|
09/12/2016
|
Submit revised proposal over an extent of 159.05ha
|
|
|
10
|
User Agency (sdkhatavkar@gmail.com)
|
REPLY
|
DFO (Bellary)
|
14/12/2016
|
The correction have been made as per the instruction received
|
|
|
11
|
DFO (Bellary)
|
EDS
|
User Agency (sdkhatavkar@gmail.com)
|
21/11/2017
|
Requested to submit the above documents through Assistant Conservator of Forests, Bellary with in time limit specified in flow chart issued by the CEC
|
|
|
12
|
User Agency (sdkhatavkar@gmail.com)
|
REPLY
|
DFO (Bellary)
|
09/12/2017
|
The correction have been made as per the instruction received
|
|
|
13
|
DFO (Bellary)
|
EDS
|
User Agency (sdkhatavkar@gmail.com)
|
13/03/2018
|
Go through uploaded letter
|
|
|
14
|
User Agency (sdkhatavkar@gmail.com)
|
REPLY
|
DFO (Bellary)
|
19/04/2018
|
The correction have been made as per the instruction received
|
|
|
15
|
DFO (Bellary)
|
EDS
|
User Agency (sdkhatavkar@gmail.com)
|
16/07/2018
|
pl submit complete proposal with CA land as per uploaded letter
|
|
|
16
|
User Agency (sdkhatavkar@gmail.com)
|
REPLY
|
DFO (Bellary)
|
21/07/2018
|
The correction have been made as per the instruction received
|
|
|
17
|
State secretary
|
EDS
|
Nodal Officer
|
20/02/2021
|
STATUS OF THE PROPOSAL
|
|
|
18
|
Nodal Officer
|
REPLY
|
State secretary
|
18/03/2021
|
Uploaded.
|
|
|
19
|
State secretary
|
EDS
|
Nodal Officer
|
05/07/2023
|
eds
|
|
|
20
|
Nodal Officer
|
EDS
|
CF (Bellary)
|
15/11/2023
|
EDS
|
|
|
21
|
CF (Bellary)
|
EDS
|
DFO (Bellary)
|
17/11/2023
|
Submit information
|
|
|
22
|
DFO (Bellary)
|
EDS
|
User Agency (envdiom@gmail.com)
|
23/11/2023
|
Please submit the complete proposal as per uploaded letter
|
|
|
23
|
User Agency (envdiom@gmail.com)
|
REPLY
|
DFO (Bellary)
|
20/03/2024
|
The correction have been made as per the instruction received
|
|
|
24
|
DFO (Bellary)
|
EDS
|
User Agency (envdiom@gmail.com)
|
23/07/2024
|
Please submit the complete proposal as per uploaded letter
|
|
|
25
|
User Agency (envdiom@gmail.com)
|
REPLY
|
DFO (Bellary)
|
29/10/2024
|
The correction have been made as per the instruction received
|
|
|
26
|
DFO (Bellary)
|
EDS
|
User Agency (envdiom@gmail.com)
|
26/06/2025
|
Submit the information as per uploaded letter
|
|
|
27
|
User Agency (envdiom@gmail.com)
|
REPLY
|
DFO (Bellary)
|
30/09/2025
|
The correction have been made as per the instruction received
|
|
|
28
|
DFO (Bellary)
|
EDS
|
User Agency (envdiom@gmail.com)
|
06/10/2025
|
It is directed to correction all data for 101.52 Ha
|
|
|
29
|
User Agency (envdiom@gmail.com)
|
REPLY
|
DFO (Bellary)
|
06/11/2025
|
The correction have been made as per the instruction received
|
|
|
30
|
DFO (Bellary)
|
EDS
|
User Agency (envdiom@gmail.com)
|
23/12/2025
|
You are hereby directed to revise the tree enumeration list for an extent of 101.52 Ha in consultation with field officers and submit through the Range Forest officer, Sandur South Range, Sandur for further processing of this proposal
|
|
|
31
|
User Agency (envdiom@gmail.com)
|
REPLY
|
DFO (Bellary)
|
12/03/2026
|
The correction have been made as per the instruction received
|
|