Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Chitradurga)
|
EDS
|
User Agency (nandan.bhandary@jsw.in)
|
17/06/2020
|
you have not submitted 9 original files for the project so far This office will not be able to inspect the location and submit a report Hence you are hereby directed to submit the 9 original files to this office the earliest for further action
|
|
2
|
User Agency (nandan.bhandary@jsw.in)
|
REPLY
|
DFO (Chitradurga)
|
06/07/2020
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Chitradurga)
|
EDS
|
User Agency (nandan.bhandary@jsw.in)
|
30/09/2020
|
The GPS readings which are marked on the maps are mis matching with ground truthing Therfore it is conveyed to user agency to rectifiy the mis matching of GPS readings both on field as wells as on maps
|
|
4
|
User Agency (nandan.bhandary@jsw.in)
|
REPLY
|
DFO (Chitradurga)
|
01/10/2020
|
The correction have been made as per the instruction received
|
|
5
|
Head Office
|
EDS
|
State secretary
|
20/07/2021
|
eds
|
|
6
|
State secretary
|
EDS
|
Nodal Officer
|
21/08/2021
|
Pls furnish the details
|
|
7
|
Nodal Officer
|
EDS
|
CF (Bellary)
|
24/08/2021
|
GOI EDS query
|
|
8
|
CF (Bellary)
|
EDS
|
DFO (Chitradurga)
|
08/09/2021
|
Submit the EDS as sought for by the GOI.
|
|
9
|
DFO (Chitradurga)
|
EDS
|
User Agency (nandan.bhandary@jsw.in)
|
28/12/2021
|
Please submit the GoI required information
|
|
10
|
User Agency (nandan.bhandary@jsw.in)
|
REPLY
|
DFO (Chitradurga)
|
29/12/2021
|
The correction have been made as per the instruction received
|
|
11
|
DFO (Chitradurga)
|
REPLY
|
CF (Bellary)
|
20/04/2022
|
submitting the information/documents as sought by the Government of India
|
|
12
|
CF (Bellary)
|
EDS
|
DFO (Chitradurga)
|
22/04/2022
|
Submit the relevant information as sought for by the GOI.
|
|
13
|
DFO (Chitradurga)
|
REPLY
|
CF (Bellary)
|
22/04/2022
|
submitting the information/documents as sought by the Government of India
|
|
14
|
CF (Bellary)
|
REPLY
|
Nodal Officer
|
01/06/2022
|
KML Files details submitted.
|
|
15
|
Nodal Officer
|
REPLY
|
State secretary
|
20/06/2022
|
GOI EDS reply
|
|
16
|
State secretary
|
EDS
|
Nodal Officer
|
22/06/2022
|
eds
|
|
17
|
Nodal Officer
|
REPLY
|
State secretary
|
30/06/2022
|
EDS reply has already submitted on 20-06-2022 same is enclosed
|
|
18
|
State secretary
|
REPLY
|
Head Office
|
15/07/2023
|
eds
|
|
19
|
Head Office
|
EDS
|
State secretary
|
03/08/2023
|
EDS
|
|