TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/KA/MIN/39394/2019              (ii). Name of Project for which Forest Land is required : R.I.O.M. M.L. No. 2141_Closed Pipe Conveyor Project              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The said project is to install closed pipe conveyor at R.I.O.M. M.L. no 2141 mine. wherein part the conveyor belt, service roads, hopper, Water Pipe Line, Transmission Lines and railway sidings come under forest land. therefore forest land is required. for the same.              (iv). File no. : 8-286/1988-FC Vol.              (v). State : Karnataka              (vi). Category of the Project : Mining              (vii). Shape of forest land proposed to be diverted : Non Linear              (viii). Area of forest land proposed for diversion(in ha.): 12.4724
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeROHQ, New DelhiStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/KA/MIN/39394/201913/03/201906/06/2019  08/05/2019  26/03/2019   10/07/2019  18/05/2019  29/04/2019   08/08/2019   23/08/2019 Bellary :26/08/2019Bellary:
  15/12/2019 (Bellary)

Karnataka:
02/01/2020
Karnataka:
11/02/2020
Bangalore:
20/07/2020
24/03/2022
By :Head Office
Karnataka
19/09/2024
07/11/2024
By :Head Office
  
C. Essential Details Sought History
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by MoEFCC,New Delhi on 16/10/2020  
Replied by State Government (Karnataka) on:21/06/2021  
Query raised by MoEFCC,New Delhi on 13/08/2021  
Replied by State Government (Karnataka) on:21/01/2022  
Query raised by State Government (Karnataka) on:21/04/2020  
Replied by Nodal Officer (Karnataka) on:06/05/2020  
Query raised by State Government (Karnataka) on:06/11/2020  
Replied by Nodal Officer (Karnataka) on:29/03/2021  
Query raised by State Government (Karnataka) on:07/06/2021  
Replied by Nodal Officer (Karnataka) on:18/06/2021  
Query raised by State Government (Karnataka) on:13/09/2021  
Replied by Nodal Officer (Karnataka) on:14/01/2022  
Query raised by Nodal Officer (Karnataka) on:09/11/2020  
Replied by Circle(Bellary) on:09/03/2021  
Query raised by Nodal Officer (Karnataka) on:26/03/2021  
Replied by Circle(Bellary) on:29/03/2021  
Query raised by Nodal Officer (Karnataka) on:14/09/2021  
Replied by Circle(Bellary) on:03/01/2022  
Query raised by Circle (Bellary) on:21/12/2019  
Replied by DFO (Bellary) on:31/12/2019  
Query raised by Circle (Bellary) on:17/11/2020  
Replied by DFO (Bellary) on:18/02/2021  
Query raised by Circle (Bellary) on:15/09/2021  
Replied by DFO (Bellary) on:21/12/2021  
Query raised by DFO (Bellary) on:26/11/2019  
Replied by UA on :27/11/2019  
Query raised by DFO (Bellary) on:22/10/2021  
Replied by UA on :04/12/2021  
D. Essential Details Sought History (Stage-II)
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by MoEFCC,New Delhi 08/10/2024  
Replied by State Government (Karnataka) on:23/10/2024  
NOTE:- Stage-II Approval accorded by : Head Office .
Close(X)