TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/KA/MIN/32568/2018              (ii). Name of Project for which Forest Land is required : DEVADARI IRON ORE MINE              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : KIOCL LIMITED (Formerly Kudremukh Iron Ore Company Limited) is a Government of India undertaking established in the year 1976 under Ministry of Steel and is operating Iron ore Pellet plant of capacity 3.5 million tons per annum and Blast Furnace Unit of capacity 2.16 lakh tons per annum at Mangalore              (iv). File no. : 8-24/2020-FC              (v). State : Karnataka              (vi). Category of the Project : Mining              (vii). Shape of forest land proposed to be diverted : Non Linear              (viii). Area of forest land proposed for diversion(in ha.): 484.0733
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentMoEFCC,New DelhiRegional Office(SIR) uploaded onStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/KA/MIN/32568/201816/03/201825/07/2018  04/04/2018   27/07/2018  28/06/2018   23/08/2018   29/08/2018 Bellary :30/08/2018Bellary:
  13/11/2019 (Bellary)

Karnataka:
07/12/2019
Karnataka:
19/02/2020
13/10/202024/06/2021
By :Head Office
Karnataka
18/08/2022
16/12/2022
By :Head Office
  
C. Essential Details Sought History
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by MoEFCC,New Delhi on 26/11/2020  
Replied by State Government (Karnataka) on:01/01/2021  
Query raised by MoEFCC,New Delhi on 03/02/2021  
Replied by State Government (Karnataka) on:10/02/2021  
Query raised by MoEFCC,New Delhi on 11/03/2021  
Replied by State Government (Karnataka) on:24/06/2021  
Query raised by State Government (Karnataka) on:16/06/2020  
Replied by Nodal Officer (Karnataka) on:13/10/2020  
Query raised by Nodal Officer (Karnataka) on:10/01/2020  
Replied by Circle(Bellary) on:19/02/2020  
Query raised by Nodal Officer (Karnataka) on:25/06/2020  
Replied by Circle(Bellary) on:13/08/2020  
Query raised by Nodal Officer (Karnataka) on:01/09/2020  
Replied by Circle(Bellary) on:09/10/2020  
Query raised by Circle (Bellary) on:04/07/2020  
Replied by DFO (Bellary) on:13/08/2020  
Query raised by Circle (Bellary) on:22/09/2020  
Replied by DFO (Bellary) on:06/10/2020  
Query raised by DFO (Bellary) on:19/11/2018  
Replied by UA on :05/12/2018  
Query raised by DFO (Bellary) on:23/01/2019  
Replied by UA on :26/04/2019  
NOTE:- Stage-II Approval accorded by : Head Office .