| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
DFO (Chitradurga)
|
EDS
|
User Agency (meghna.ghosh@vedanta.co.in)
|
22/01/2024
|
It is not possible to inspect the above proposal site as the temporary boundary is not marked at the place by putting demarcation stones at every 20 mtr apart
|
|
|
2
|
User Agency (meghna.ghosh@vedanta.co.in)
|
REPLY
|
DFO (Chitradurga)
|
19/06/2024
|
The correction have been made as per the instruction received
|
|
|
3
|
DFO (Chitradurga)
|
EDS
|
User Agency (meghna.ghosh@vedanta.co.in)
|
13/09/2024
|
The Range forest officer Holalkere Range Holalkere was inspected on 14 08 2024 to the above proposal site with your company staff and the following observations were made during the site inspection
It is not mentioned the actually extent in your lease boundary of Gate 3
Therefore it has been requetsed to actually mention the extent at the above proposal and submit a revised maps with GPS reading to this office the earliest for further action
|
|
|
4
|
User Agency (meghna.ghosh@vedanta.co.in)
|
REPLY
|
DFO (Chitradurga)
|
26/09/2024
|
The correction have been made as per the instruction received
|
|
|
5
|
DFO (Chitradurga)
|
EDS
|
User Agency (meghna.ghosh@vedanta.co.in)
|
23/10/2024
|
The Range forest officer Holalkere Range Holalkere was inspected the site on 19 10 2024 the following observations were again made during the site inspection
It is not mentioned the actually extent in your lease boundary of Gate 3
You have not co-operated to identify the boundary
Therefore it has been requetsed to actually mention the extent in the above proposal and submit a revised maps with GPS reading to this office at the earliest for further action
|
|
|
6
|
User Agency (meghna.ghosh@vedanta.co.in)
|
REPLY
|
DFO (Chitradurga)
|
02/12/2024
|
The correction have been made as per the instruction received
|
|
|
7
|
State secretary
|
EDS
|
Nodal Officer
|
07/02/2025
|
eds
|
|
|
8
|
Nodal Officer
|
REPLY
|
State secretary
|
13/02/2025
|
EDS reply
|
|
|
9
|
Head Office
|
EDS
|
State secretary
|
05/05/2025
|
EDS
|
|
|
10
|
State secretary
|
EDS
|
Nodal Officer
|
15/05/2025
|
eds
|
|
|
11
|
Nodal Officer
|
EDS
|
CF (Bellary)
|
02/06/2025
|
EDS communication
|
|
|
12
|
CF (Bellary)
|
EDS
|
DFO (Chitradurga)
|
04/06/2025
|
Submit the information as sought by the PCCF FC
|
|
|
13
|
DFO (Chitradurga)
|
EDS
|
User Agency (meghna.ghosh@vedanta.co.in)
|
10/06/2025
|
The Principal Conservator of Forest Forest Conservation and Nodal officer FCA aranya Bhavan Bengaluru vide letter dated 30 05 2025 has directed to furnish the documents clarification information required for further processing of the proposal
|
|
|
14
|
User Agency (meghna.ghosh@vedanta.co.in)
|
REPLY
|
DFO (Chitradurga)
|
18/06/2025
|
The correction have been made as per the instruction received
|
|
|
15
|
DFO (Chitradurga)
|
REPLY
|
CF (Bellary)
|
25/08/2025
|
As per PCCF office vide letter 30 05 2025 submitted to information documents
|
|
|
16
|
CF (Bellary)
|
EDS
|
DFO (Chitradurga)
|
08/10/2025
|
Submit the information
|
|
|
17
|
DFO (Chitradurga)
|
REPLY
|
CF (Bellary)
|
08/10/2025
|
information as sought is submitted for your kind perusal and needful action sir
|
|
|
18
|
CF (Bellary)
|
EDS
|
DFO (Chitradurga)
|
08/10/2025
|
Submit the information
|
|
|
19
|
DFO (Chitradurga)
|
REPLY
|
CF (Bellary)
|
08/10/2025
|
information as sought is submitted for your kind perusal and needful action sir
|
|
|
20
|
CF (Bellary)
|
EDS
|
DFO (Chitradurga)
|
14/10/2025
|
Submit the information regarding conditions No. 14 with relevant documents
|
|
|
21
|
DFO (Chitradurga)
|
EDS
|
User Agency (meghna.ghosh@vedanta.co.in)
|
20/11/2025
|
the Principal Chief Conservator of Forests, Bengaluru has directed that the latest report regarding compliance with the conditions under item no 4 of the office letter dated 30 05 2025 be submitted to this office through the Range Forest Officer Holalkere Range Holalkere and the Assistant Conservator of Forests Chitradurga Sub Division Chitradurga to this office six copies
|
|
|
22
|
User Agency (meghna.ghosh@vedanta.co.in)
|
REPLY
|
DFO (Chitradurga)
|
02/01/2026
|
The correction have been made as per the instruction received
|
|
|
23
|
DFO (Chitradurga)
|
EDS
|
User Agency (meghna.ghosh@vedanta.co.in)
|
09/01/2026
|
But you have not submitted original documets for the project so far This office will not be able to inspect the location and submit a report Hence you are hereby directed to submit the latest report regarding compliance with the conditions under item no 4 of the office letter dated 30 05 2025 and 15 11 2025
|
|
|
24
|
User Agency (meghna.ghosh@vedanta.co.in)
|
REPLY
|
DFO (Chitradurga)
|
29/04/2026
|
The correction have been made as per the instruction received
|
|
|
25
|
DFO (Chitradurga)
|
REPLY
|
CF (Bellary)
|
29/04/2026
|
The copy of the latest compliance report for the period April 2025 to March 2026 is enclosed
|
|