Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Chitradurga)
|
EDS
|
User Agency (meghna.ghosh@vedanta.co.in)
|
22/01/2024
|
It is not possible to inspect the above proposal site as the temporary boundary is not marked at the place by putting demarcation stones at every 20 mtr apart
|
|
2
|
User Agency (meghna.ghosh@vedanta.co.in)
|
REPLY
|
DFO (Chitradurga)
|
19/06/2024
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Chitradurga)
|
EDS
|
User Agency (meghna.ghosh@vedanta.co.in)
|
13/09/2024
|
The Range forest officer Holalkere Range Holalkere was inspected on 14 08 2024 to the above proposal site with your company staff and the following observations were made during the site inspection
It is not mentioned the actually extent in your lease boundary of Gate 3
Therefore it has been requetsed to actually mention the extent at the above proposal and submit a revised maps with GPS reading to this office the earliest for further action
|
|
4
|
User Agency (meghna.ghosh@vedanta.co.in)
|
REPLY
|
DFO (Chitradurga)
|
26/09/2024
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Chitradurga)
|
EDS
|
User Agency (meghna.ghosh@vedanta.co.in)
|
23/10/2024
|
The Range forest officer Holalkere Range Holalkere was inspected the site on 19 10 2024 the following observations were again made during the site inspection
It is not mentioned the actually extent in your lease boundary of Gate 3
You have not co-operated to identify the boundary
Therefore it has been requetsed to actually mention the extent in the above proposal and submit a revised maps with GPS reading to this office at the earliest for further action
|
|
6
|
User Agency (meghna.ghosh@vedanta.co.in)
|
REPLY
|
DFO (Chitradurga)
|
02/12/2024
|
The correction have been made as per the instruction received
|
|
7
|
State secretary
|
EDS
|
Nodal Officer
|
07/02/2025
|
eds
|
|
8
|
Nodal Officer
|
REPLY
|
State secretary
|
13/02/2025
|
EDS reply
|
|
9
|
Head Office
|
EDS
|
State secretary
|
05/05/2025
|
EDS
|
|
10
|
State secretary
|
EDS
|
Nodal Officer
|
15/05/2025
|
eds
|
|
11
|
Nodal Officer
|
EDS
|
CF (Bellary)
|
02/06/2025
|
EDS communication
|
|
12
|
CF (Bellary)
|
EDS
|
DFO (Chitradurga)
|
04/06/2025
|
Submit the information as sought by the PCCF FC
|
|
13
|
DFO (Chitradurga)
|
EDS
|
User Agency (meghna.ghosh@vedanta.co.in)
|
10/06/2025
|
The Principal Conservator of Forest Forest Conservation and Nodal officer FCA aranya Bhavan Bengaluru vide letter dated 30 05 2025 has directed to furnish the documents clarification information required for further processing of the proposal
|
|
14
|
User Agency (meghna.ghosh@vedanta.co.in)
|
REPLY
|
DFO (Chitradurga)
|
18/06/2025
|
The correction have been made as per the instruction received
|
|
15
|
DFO (Chitradurga)
|
REPLY
|
CF (Bellary)
|
25/08/2025
|
As per PCCF office vide letter 30 05 2025 submitted to information documents
|
|