  (i). Proposal No. : FP/KA/IRRIG/17555/2016              (ii). Name of Project for which Forest Land is required : Construction of Aqueduct for Dy-2 Under UTP Main Canal              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Construction of Aqueduct from Ch 40.409 to 41.450 km and 41.820 to 42.135 km of Distributory no-2 under UTP Main Canal              (iv). File no. : FEE 42 FLL 2016              (v). State : Karnataka              (vi). Category of the Project : Irrigation              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.5404
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/KA/IRRIG/17555/201615/01/201609/02/2016  21/01/2016   09/02/2016  23/01/2016   29/01/2016   09/02/2016 Haveri :15/02/2016Dharwad:
  11/03/2016 (Haveri)

Karnataka:
24/03/2016
Karnataka:
30/03/2016
04/05/2016
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
  
NOTE:- Stage-I Approval accorded by : State Government .