Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Gokak)
|
EDS
|
User Agency (envifor.irepka@greenkoenergyprojects.com)
|
24/08/2019
|
Submission of copy
|
|
2
|
User Agency (envifor.irepka@greenkoenergyprojects.com)
|
REPLY
|
DFO (Gokak)
|
29/09/2019
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Gokak)
|
EDS
|
User Agency (envifor.irepka@greenkoenergyprojects.com)
|
05/10/2019
|
verify and submit the proposed area
|
|
4
|
User Agency (envifor.irepka@greenkoenergyprojects.com)
|
REPLY
|
DFO (Gokak)
|
11/10/2019
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Gokak)
|
EDS
|
User Agency (envifor.irepka@greenkoenergyprojects.com)
|
19/12/2019
|
kindly upload GO No AFD 453 FGL 69 dt 18.10.1969 with respect to release of land an area of 1029 Acres for the displacement of the Dhupadal and Yakkundi taluk parasgad.
|
|
6
|
User Agency (envifor.irepka@greenkoenergyprojects.com)
|
REPLY
|
DFO (Gokak)
|
28/01/2020
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Gokak)
|
EDS
|
User Agency (envifor.irepka@greenkoenergyprojects.com)
|
07/03/2020
|
uploaded this office letter reg- essential details
|
|
8
|
User Agency (envifor.irepka@greenkoenergyprojects.com)
|
REPLY
|
DFO (Gokak)
|
10/06/2020
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Gokak)
|
EDS
|
User Agency (envifor.irepka@greenkoenergyprojects.com)
|
11/06/2020
|
Submission of Govt Order Copy.
|
|
10
|
User Agency (envifor.irepka@greenkoenergyprojects.com)
|
REPLY
|
DFO (Gokak)
|
14/06/2020
|
The correction have been made as per the instruction received
|
|
11
|
CF (Belgaum)
|
EDS
|
DFO (Gokak)
|
08/09/2020
|
This proposal incomplete please provide the essential details as per the this office letter dated 07-09-2020
|
|
12
|
DFO (Gokak)
|
EDS
|
User Agency (envifor.irepka@greenkoenergyprojects.com)
|
11/09/2020
|
Kindly upload the documents letter dated 11.09.2020 of this office.
|
|
13
|
User Agency (envifor.irepka@greenkoenergyprojects.com)
|
REPLY
|
DFO (Gokak)
|
09/04/2021
|
The correction have been made as per the instruction received
|
|
14
|
DFO (Gokak)
|
REPLY
|
CF (Belgaum)
|
16/04/2021
|
With regard to your EDS letter dated 07.09.2020, Site Inspection has been carried out by me on 12.04.2021. Detailed Site Inspection report in this regard along with my recommendations are enclosed. Further, detailed reply as submitted by User Agency is also enclosed for your kind perusal.
|
|
15
|
CF (Belgaum)
|
EDS
|
DFO (Gokak)
|
22/04/2021
|
This proposal incomplete please provide the essential details as per the this office letter dated 21-04-2021
|
|
16
|
DFO (Gokak)
|
REPLY
|
CF (Belgaum)
|
23/04/2021
|
Reply to your EDS letter date:22-04-2021.
|
|
17
|
CF (Belgaum)
|
EDS
|
DFO (Gokak)
|
12/05/2021
|
This proposal incomplete please provide the essential details as per the this office letter dated 11-05-2021
|
|
18
|
DFO (Gokak)
|
REPLY
|
CF (Belgaum)
|
17/05/2021
|
Field inspection report sought by Chief Conservator for forest Belagavi Circle Belagavi
|
|
19
|
Head Office
|
EDS
|
State secretary
|
02/12/2021
|
EDS
|
|
20
|
State secretary
|
EDS
|
Nodal Officer
|
03/12/2021
|
eds
|
|
21
|
Nodal Officer
|
EDS
|
CF (Belgaum)
|
09/12/2021
|
submit the clarification/information sought by GOI
|
|
22
|
CF (Belgaum)
|
EDS
|
DFO (Gokak)
|
09/12/2021
|
please submit the clarification/information sought by GOI
|
|
23
|
DFO (Gokak)
|
EDS
|
User Agency (envifor.irepka@greenkoenergyprojects.com)
|
10/12/2021
|
Submit that clarification for information submitted by Government of India.
|
|
24
|
User Agency (envifor.irepka@greenkoenergyprojects.com)
|
REPLY
|
DFO (Gokak)
|
13/12/2021
|
The correction have been made as per the instruction received
|
|
25
|
DFO (Gokak)
|
REPLY
|
CF (Belgaum)
|
18/12/2021
|
Reply to EDS querry raised by GOI
|
|
26
|
CF (Belgaum)
|
REPLY
|
Nodal Officer
|
24/12/2021
|
Compliance Report submitted as per this office letter dated: 24-12-2021.
|
|
27
|
Nodal Officer
|
REPLY
|
State secretary
|
14/01/2022
|
the details obtained from Field Officers and UA is submitted for further processing
|
|
28
|
State secretary
|
REPLY
|
Head Office
|
14/01/2022
|
reply to query dated 01.12.2021
|
|
29
|
Head Office
|
EDS
|
State secretary
|
24/02/2022
|
eds
|
|
30
|
State secretary
|
EDS
|
Nodal Officer
|
25/02/2022
|
eds
|
|
31
|
Nodal Officer
|
REPLY
|
State secretary
|
09/03/2022
|
the information documents sought by GOI is submitted herewith for approval
|
|
32
|
State secretary
|
REPLY
|
Head Office
|
10/03/2022
|
eds
|
|
33
|
Head Office
|
EDS
|
State secretary
|
08/04/2022
|
eds
|
|
34
|
State secretary
|
EDS
|
Nodal Officer
|
19/04/2022
|
eds
|
|
35
|
Nodal Officer
|
EDS
|
CF (Belgaum)
|
22/04/2022
|
EDS query
|
|
36
|
CF (Belgaum)
|
EDS
|
DFO (Gokak)
|
22/04/2022
|
EDS query
|
|
37
|
DFO (Gokak)
|
EDS
|
User Agency (envifor.irepka@greenkoenergyprojects.com)
|
26/04/2022
|
Further action by UA
|
|
38
|
User Agency (envifor.irepka@greenkoenergyprojects.com)
|
REPLY
|
DFO (Gokak)
|
29/04/2022
|
The correction have been made as per the instruction received
|
|
39
|
DFO (Gokak)
|
REPLY
|
CF (Belgaum)
|
04/05/2022
|
EDS replay & CAT plan submitted for acceptance
|
|
40
|
CF (Belgaum)
|
REPLY
|
Nodal Officer
|
06/05/2022
|
EDS quarries reply as per this office Letter Dated: 06-05-2022.
|
|
41
|
Nodal Officer
|
REPLY
|
State secretary
|
07/05/2022
|
the reply submitted for your information
|
|
42
|
State secretary
|
REPLY
|
Head Office
|
09/05/2022
|
eds
|
|