TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/KA/HYD/37723/2018              (ii). Name of Project for which Forest Land is required : Standalone Pumped Storage Component of Saundatti IREP              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : India is leading the world’s renewable energy revolution and is on track to achieve 175 GW of RE capacity by 2022. Today, Wind & Solar, are the lowest cost source of new energy, however their inherent infirm nature & non-schedulability presents a huge challenge for integrating large RE capacities.              (iv). File no. : 8-29/2021-FC              (v). State : Karnataka              (vi). Category of the Project : Hydel              (vii). Shape of forest land proposed to be diverted : Non Linear              (viii). Area of forest land proposed for diversion(in ha.): 160.4
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentMoEFCC,New DelhiRegional Office(SIR) uploaded onStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/KA/HYD/37723/201818/12/201830/05/2019  15/03/2019  14/01/2019   03/06/2019  06/05/2019  19/02/2019   15/06/2019   19/06/2019 Gokak :21/06/2019Belgaum:
  22/04/2021 (Gokak)

Karnataka:
18/05/2021
Karnataka:
16/08/2021
18/11/202112/07/2022
By :Head Office
Karnataka
24/04/2024
21/08/2024
By :Head Office
  
C. Essential Details Sought History
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by MoEFCC,New Delhi on 02/12/2021  
Replied by State Government (Karnataka) on:14/01/2022  
Query raised by MoEFCC,New Delhi on 24/02/2022  
Replied by State Government (Karnataka) on:10/03/2022  
Query raised by MoEFCC,New Delhi on 08/04/2022  
Replied by State Government (Karnataka) on:09/05/2022  
Query raised by State Government (Karnataka) on:03/12/2021  
Replied by Nodal Officer (Karnataka) on:14/01/2022  
Query raised by State Government (Karnataka) on:25/02/2022  
Replied by Nodal Officer (Karnataka) on:09/03/2022  
Query raised by State Government (Karnataka) on:19/04/2022  
Replied by Nodal Officer (Karnataka) on:07/05/2022  
Query raised by Nodal Officer (Karnataka) on:09/12/2021  
Replied by Circle(Belgaum) on:24/12/2021  
Query raised by Nodal Officer (Karnataka) on:22/04/2022  
Replied by Circle(Belgaum) on:06/05/2022  
Query raised by Circle (Belgaum) on:08/09/2020  
Replied by DFO (Gokak) on:16/04/2021  
Query raised by Circle (Belgaum) on:22/04/2021  
Replied by DFO (Gokak) on:23/04/2021  
Query raised by Circle (Belgaum) on:12/05/2021  
Replied by DFO (Gokak) on:17/05/2021  
Query raised by Circle (Belgaum) on:09/12/2021  
Replied by DFO (Gokak) on:18/12/2021  
Query raised by Circle (Belgaum) on:22/04/2022  
Replied by DFO (Gokak) on:04/05/2022  
Query raised by DFO (Gokak) on:24/08/2019  
Replied by UA on :29/09/2019  
Query raised by DFO (Gokak) on:05/10/2019  
Replied by UA on :11/10/2019  
Query raised by DFO (Gokak) on:19/12/2019  
Replied by UA on :28/01/2020  
Query raised by DFO (Gokak) on:07/03/2020  
Replied by UA on :10/06/2020  
Query raised by DFO (Gokak) on:11/06/2020  
Replied by UA on :14/06/2020  
Query raised by DFO (Gokak) on:11/09/2020  
Replied by UA on :09/04/2021  
Query raised by DFO (Gokak) on:10/12/2021  
Replied by UA on :13/12/2021  
Query raised by DFO (Gokak) on:26/04/2022  
Replied by UA on :29/04/2022  
D. Essential Details Sought History (Stage-II)
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by MoEFCC,New Delhi 10/05/2024  
Replied by State Government (Karnataka) on:02/08/2024  
Query raised by State Government (Karnataka) on:17/05/2024  
Replied by Nodal Officer (Karnataka) on:28/06/2024  
Query raised by Nodal Officer on:23/05/2024  
Replied by UA on :13/06/2024  
NOTE:- Stage-II Approval accorded by : Head Office .