TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/KA/Canal/38030/2019              (ii). Name of Project for which Forest Land is required : Modification to Stage II approved FC proposal involving diversion of 111.57 Ha of forest land in Jankal, Devaragudda and Lakkihalli Reserve Forest of Hosadurga and Hiriyur Forest Ranges, Chitradurga Forest Division for construction of Chitradurga Branch Canal.              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Upper Bhadra project envisages lifting of 17.40TMC of water in first stage from Tunga River to existing Bhadra reservoir and lifting of 29.90 TMC of water in second stage from Bhadra reservoir to Tunnel near Ajjampura in Tungabhadra sub-basin of Krishna basin. After Tunnel, through Chitradurga Branc              (iv). State : Karnataka              (v). Category of the Project : Canal              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 103.6
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/KA/Canal/38030/201903/01/201910/12/2019  11/09/2019  01/02/2019   05/06/2020  15/11/2019  27/07/2019   30/06/2020   24/07/2020

Chikkamagalur :29/07/2020


Chitradurga :29/07/2020

  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by DFO (Chitradurga) on:16/09/2020  
Replied by UA on :05/02/2021  
Query raised by DFO (Chitradurga) on:10/08/2021  
Replied by UA on :21/08/2021  
Query raised by DFO (Chitradurga) on:30/08/2022  
Replied by UA on :14/09/2022  
Query raised by DFO (Chikkamagalur) on:27/07/2023  
Replied by UA on :07/08/2023  
Query raised by DFO (Chitradurga) on:03/10/2023  
Replied by UA on :03/10/2023  
Query raised by DFO (Chitradurga) on:03/10/2023  
Replied by UA on :18/10/2023  
NOTE:- Proposal is pending at DFO .