TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/KA/Approach/47989/2020              (ii). Name of Project for which Forest Land is required : Diversion of forest land in keligeri village, Dharward Taluk for additional interconnectivity between the two ends of the arch shaped campus of Indian Institute of Technology,Dharwad              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : A stretch of land of about 0.66ha is required as internal road connecting two prime locations, namely, academic zone and residential zone which is essential to make it an integral part of the campus. The internal road will make the campus contiguous joining the two critical and essential link. It wi              (iv). File no. : F.No.4-KRB1341/2022-BAN              (v). State : Karnataka              (vi). Category of the Project : Approach Access              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.66
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/KA/Approach/47989/202029/07/202013/11/2020  12/10/2020  27/08/2020   07/01/2021  21/10/2020  24/09/2020   13/01/2021   28/01/2021 Dharwad :28/01/2021Dharwad:
  05/07/2021 (Dharwad)

Karnataka:
25/11/2021
Karnataka:
12/01/2022
Bangalore:
24/02/2022
08/03/2023
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Bangalore) on:11/03/2022  
Replied by State Government(Karnataka) on:06/03/2023  
Query raised by State Government (Karnataka) on:22/03/2022  
Replied by Nodal Officer (Karnataka) on:14/02/2023  
Query raised by Nodal Officer (Karnataka) on:07/04/2022  
Replied by Circle(Dharwad) on:25/01/2023  
Query raised by Circle (Dharwad) on:28/04/2022  
Replied by DFO (Dharwad) on:23/01/2023  
Query raised by DFO (Dharwad) on:25/03/2021  
Replied by UA on :31/03/2021  
Query raised by DFO (Dharwad) on:04/05/2022  
Replied by UA on :06/01/2023  
Query raised by DFO (Dharwad) on:06/01/2023  
Replied by UA on :19/01/2023  
NOTE:- Stage-I Approval accorded by : Regional Office .
Close(X)