Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
CF (Belgaum)
|
EDS
|
DFO (Belgaum)
|
04/12/2020
|
The DCF Belagavi was submitted incomplete proposal. Hence proposal is return to DCF Belagavi, Please provide the details as per this office letter dted 4-12-2020
|
|
2
|
DFO (Belgaum)
|
EDS
|
User Agency (eepwdbgm@gmail.com)
|
11/12/2020
|
Please reply to eds
|
|
3
|
User Agency (eepwdbgm@gmail.com)
|
REPLY
|
DFO (Belgaum)
|
15/07/2021
|
The correction have been made as per the instruction received
|
|
4
|
DFO (Belgaum)
|
REPLY
|
CF (Belgaum)
|
12/11/2021
|
Compliance to the CCF, Belagavi letter dated : 04-12-2020.
|
|
5
|
CF (Belgaum)
|
EDS
|
DFO (Belgaum)
|
25/11/2021
|
Plz.. verify Elephant Corridor, ESZ area. plz submitted immediate
|
|
6
|
DFO (Belgaum)
|
REPLY
|
CF (Belgaum)
|
03/12/2021
|
Submitting Compliance report to the CCF, Belagavi
|
|