Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Kamraj Forest Division)
|
EDS
|
User Agency (xenphekupwara11@gmail.com)
|
19/07/2021
|
EDS with respect of proposal No.FP/JK/WATER/144060/2021 dt.26.06.2021
|
|
2
|
User Agency (xenphekupwara11@gmail.com)
|
REPLY
|
DFO (Kamraj Forest Division)
|
01/08/2021
|
The correction have been made as per the instruction received
|
|
3
|
CF (North Circle Sopore)
|
EDS
|
DFO (Kamraj Forest Division)
|
06/08/2021
|
correction in CA sites
|
|
4
|
DFO (Kamraj Forest Division)
|
REPLY
|
CF (North Circle Sopore)
|
06/08/2021
|
Sir,
Necessary corrections have been made.
|
|
5
|
CF (North Circle Sopore)
|
EDS
|
DFO (Kamraj Forest Division)
|
12/08/2021
|
Please make necessary corrections as per EDS
|
|
6
|
DFO (Kamraj Forest Division)
|
EDS
|
User Agency (xenphekupwara11@gmail.com)
|
13/08/2021
|
EDS of Wani Doursa, Tekipora
|
|
7
|
User Agency (xenphekupwara11@gmail.com)
|
REPLY
|
DFO (Kamraj Forest Division)
|
13/08/2021
|
The correction have been made as per the instruction received
|
|
8
|
DFO (Kamraj Forest Division)
|
REPLY
|
CF (North Circle Sopore)
|
16/08/2021
|
The proposal completed and submit to CF North for further processing under FCA 1980
|
|
9
|
Nodal Officer
|
EDS
|
CF (North Circle Sopore)
|
21/08/2021
|
Kindly upload the requisite information please.
|
|
10
|
CF (North Circle Sopore)
|
EDS
|
DFO (Kamraj Forest Division)
|
21/08/2021
|
Please upload the requisite information as per EDS raised by Nodal Officer- FCA.
|
|
11
|
DFO (Kamraj Forest Division)
|
EDS
|
User Agency (xenphekupwara11@gmail.com)
|
21/08/2021
|
EDS of WSS Wani Doursa
|
|
12
|
User Agency (xenphekupwara11@gmail.com)
|
REPLY
|
DFO (Kamraj Forest Division)
|
07/09/2021
|
The correction have been made as per the instruction received
|
|
13
|
DFO (Kamraj Forest Division)
|
REPLY
|
CF (North Circle Sopore)
|
08/09/2021
|
The correction have been made as per the instruction received.
|
|
14
|
CF (North Circle Sopore)
|
REPLY
|
Nodal Officer
|
08/09/2021
|
Sir, necessary corrections done, please check.
|
|
15
|
State secretary
|
EDS
|
Nodal Officer
|
05/10/2021
|
EDS
|
|
16
|
Nodal Officer
|
EDS
|
CF (North Circle Sopore)
|
09/10/2021
|
Kindly upload the requisite information please.
|
|
17
|
CF (North Circle Sopore)
|
EDS
|
DFO (Kamraj Forest Division)
|
09/10/2021
|
Kindly do the necessary correction as per EDS.
|
|
18
|
DFO (Kamraj Forest Division)
|
EDS
|
User Agency (xenphekupwara11@gmail.com)
|
13/10/2021
|
EDS raised by SG in WSS Wani Doursa Tekipora as such the requisite documents and details of water pipelines of 4 inche diameter and wedth of land required for supply mans be uploaded
|
|
19
|
User Agency (xenphekupwara11@gmail.com)
|
REPLY
|
DFO (Kamraj Forest Division)
|
20/10/2021
|
The correction have been made as per the instruction received
|
|
20
|
DFO (Kamraj Forest Division)
|
REPLY
|
CF (North Circle Sopore)
|
23/10/2021
|
Sir, it is submitted that the user agency has uploaded the point wise required documents/details on parivesh portal and as such it is requested/recommended that the case may kindly be processed under the provisions of FCA, 1980 please.
|
|
21
|
CF (North Circle Sopore)
|
REPLY
|
Nodal Officer
|
28/10/2021
|
Sir, the requisite documents uploaded by UA.
|
|
22
|
Nodal Officer
|
REPLY
|
State secretary
|
03/11/2021
|
The requisite documents have been uploaded
|
|