TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/JK/WATER/144060/2021              (ii). Name of Project for which Forest Land is required : Water Supply Scheme Wani Doursa Tekipora              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The scheme consists of 4 Reservoirs, 1 pre sedimentation tank, 1 filtration plant, headworks, pump house, fencing around structures and laying and fitting of pipelines              (iv). File no. : Fst-land0FC/93/2021-02              (v). State : Jammu and Kashmir              (vi). Category of the Project : Drinking Water              (vii). Shape of forest land proposed to be diverted : Hybrid              (viii). Area of forest land proposed for diversion(in ha.): 0.5068
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentStage-I Approval onStage-II Approval on
FP/JK/WATER/144060/202126/06/2021aa28/06/2021   05/07/2021 Kamraj Forest Division :07/07/2021North Circle Sopore:
  06/08/2021 (Kamraj Forest Division)

Jammu and Kashmir:
16/08/2021
Jammu and Kashmir:
14/09/2021
26/11/2021
By :State Government
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by State Government (Jammu and Kashmir) on:05/10/2021  
Replied by Nodal Officer (Jammu and Kashmir) on:03/11/2021  
Query raised by Nodal Officer (Jammu and Kashmir) on:21/08/2021  
Replied by Circle(North Circle Sopore) on:08/09/2021  
Query raised by Nodal Officer (Jammu and Kashmir) on:09/10/2021  
Replied by Circle(North Circle Sopore) on:28/10/2021  
Query raised by Circle (North Circle Sopore) on:06/08/2021  
Replied by DFO (Kamraj Forest Division) on:06/08/2021  
Query raised by Circle (North Circle Sopore) on:12/08/2021  
Replied by DFO (Kamraj Forest Division) on:16/08/2021  
Query raised by Circle (North Circle Sopore) on:21/08/2021  
Replied by DFO (Kamraj Forest Division) on:08/09/2021  
Query raised by Circle (North Circle Sopore) on:09/10/2021  
Replied by DFO (Kamraj Forest Division) on:23/10/2021  
Query raised by DFO (Kamraj Forest Division) on:19/07/2021  
Replied by UA on :01/08/2021  
Query raised by DFO (Kamraj Forest Division) on:13/08/2021  
Replied by UA on :13/08/2021  
Query raised by DFO (Kamraj Forest Division) on:21/08/2021  
Replied by UA on :07/09/2021  
Query raised by DFO (Kamraj Forest Division) on:13/10/2021  
Replied by UA on :20/10/2021  
NOTE:- Stage-I Approval accorded by : State Government .